Commissioning of the PGU-220 Steam-Gas Power Generating Unit at the TÉTS-12 Thermal Power Plant of PJSC “Mosenergo”
From September 1, 2013, through May 31, 2015, startup-adjustment work and equipment tests for the startup system for the PGU-220 steam-gas power unit at the TÉTs-12 thermal power plant of PJSC “Mosenergo” were carried out under the leadership of the general contractor JSC “TÉK Mosenergo,” JSC “VTI,” (setup and testing of thermal and mechanical equipment) with the participation of JSC “Firma ORGRÉS” (post-installation cleaning of the boiler-utilizer and adjustment of the water-chemical treatment regime). The basic results of this commissioning activity and test startup of the power generating unit are presented.
Commissioning of the PGU-220 Steam-Gas Power Generating Unit at the TÉTS-12 Thermal Power Plant of PJSC “Mosenergo”
From September 1, 2013, through May 31, 2015, startup-adjustment work and equipment tests for the startup system for the PGU-220 steam-gas power unit at the TÉTs-12 thermal power plant of PJSC “Mosenergo” were carried out under the leadership of the general contractor JSC “TÉK Mosenergo,” JSC “VTI,” (setup and testing of thermal and mechanical equipment) with the participation of JSC “Firma ORGRÉS” (post-installation cleaning of the boiler-utilizer and adjustment of the water-chemical treatment regime). The basic results of this commissioning activity and test startup of the power generating unit are presented.
Commissioning of the PGU-220 Steam-Gas Power Generating Unit at the TÉTS-12 Thermal Power Plant of PJSC “Mosenergo”
Radin, Yu. A. (author) / Rumyantsev, S. V. (author) / Smyshlyaev, V. B. (author) / Gorlatov, D. I. (author) / Grishin, I. A. (author)
Power Technology and Engineering ; 50 ; 401-406
2016-11-01
6 pages
Article (Journal)