Applying rough random MODM model to resource-constrained project scheduling problem: A case study of Pubugou Hydropower Project in China
Abstract To improve the scheduling efficiency in the Pubugou Hydropower Project, this paper studies the practical resource-constrained project scheduling problem with multi-mode (MRCPSP) in its Construction and Decoration Systems. By taking into account the roughness and randomness in the hybrid uncertain environment, a rough random Multiple Objective Decision Making (MODM) model is presented. To deal with the complex uncertainties, the rough random expected value model is used to obtain an equivalent crisp model. Subsequently, motivated by the particular nature of MODM model, Multiple Objective Particle Swarm Optimization (MOPSO) algorithm is employed to search the Pareto optimal solutions. An practical application to Construction and Decoration Systems in Pubugou Hydropower Project is presented to verify the practicability of the proposed rough random MODM model and the efficiency of the solution algorithm.
Applying rough random MODM model to resource-constrained project scheduling problem: A case study of Pubugou Hydropower Project in China
Abstract To improve the scheduling efficiency in the Pubugou Hydropower Project, this paper studies the practical resource-constrained project scheduling problem with multi-mode (MRCPSP) in its Construction and Decoration Systems. By taking into account the roughness and randomness in the hybrid uncertain environment, a rough random Multiple Objective Decision Making (MODM) model is presented. To deal with the complex uncertainties, the rough random expected value model is used to obtain an equivalent crisp model. Subsequently, motivated by the particular nature of MODM model, Multiple Objective Particle Swarm Optimization (MOPSO) algorithm is employed to search the Pareto optimal solutions. An practical application to Construction and Decoration Systems in Pubugou Hydropower Project is presented to verify the practicability of the proposed rough random MODM model and the efficiency of the solution algorithm.
Applying rough random MODM model to resource-constrained project scheduling problem: A case study of Pubugou Hydropower Project in China
Zhang, Zhe (author) / Xu, Jiuping (author)
KSCE Journal of Civil Engineering ; 18 ; 1279-1291
2014-05-20
13 pages
Article (Journal)
Electronic Resource
English
British Library Conference Proceedings | 2012
|Dynamic analysis of earth rock fill dam in Pubugou hydraulic project
British Library Conference Proceedings | 2005
|Extensions of the resource-constrained project scheduling problem
Elsevier | 2023
|Applying Genetic Algorithm to Resource Constrained Multi-Project Scheduling Problems
British Library Online Contents | 2010
|