A Robust Bi-objective Optimization Model for Resource Levelling Project Scheduling Problem with Discounted Cash Flows
Due to limited financial resources and high costs of infrastructure projects, project stakeholders seek to gain maximum profits with optimal resource utilization as well as cost and time minimization. Therefore, this study presents a multi-mode resource-constrained project scheduling model considering the uncertain parameters of cost and time together with the goals of maximizing the net present value and minimizing resource usage fluctuation. Also, the assumptions related to the real-world projects regarding multi-mode activities, limitation of renewable resources, and the deadline of project are incorporated into the proposed model. Moreover, a robust scheduling method is presented to better deal with the inherent uncertainties of projects regarding cost and time. The model is solved with the exact method named lexicographic goal programming (LGP). Due to the NP-hardness of the problem, two metaheuristic algorithms named Non-dominated Sorting Genetic Algorithm (NSGA-II) and Multi-Objective Particle Swarm Optimization (MOPSO) are applied to solve various medium and large size problems. The obtained results indicate the high efficiency of the two metaheuristic algorithms in solving the problem and the better performance of the MOPSO algorithm compared with NSGA-II in terms of five indices. Furthermore, the model is implemented in an offshore equipment installation phase of a wellhead platform project. Finally, the sensitivity analysis of the proposed robust model is performed considering different conservation levels, and the results are evaluated by Monte Carlo simulation with three normal, uniform and triangular distributions. The findings demonstrate that the robustness of the model against the variations of uncertain parameters.
A Robust Bi-objective Optimization Model for Resource Levelling Project Scheduling Problem with Discounted Cash Flows
Due to limited financial resources and high costs of infrastructure projects, project stakeholders seek to gain maximum profits with optimal resource utilization as well as cost and time minimization. Therefore, this study presents a multi-mode resource-constrained project scheduling model considering the uncertain parameters of cost and time together with the goals of maximizing the net present value and minimizing resource usage fluctuation. Also, the assumptions related to the real-world projects regarding multi-mode activities, limitation of renewable resources, and the deadline of project are incorporated into the proposed model. Moreover, a robust scheduling method is presented to better deal with the inherent uncertainties of projects regarding cost and time. The model is solved with the exact method named lexicographic goal programming (LGP). Due to the NP-hardness of the problem, two metaheuristic algorithms named Non-dominated Sorting Genetic Algorithm (NSGA-II) and Multi-Objective Particle Swarm Optimization (MOPSO) are applied to solve various medium and large size problems. The obtained results indicate the high efficiency of the two metaheuristic algorithms in solving the problem and the better performance of the MOPSO algorithm compared with NSGA-II in terms of five indices. Furthermore, the model is implemented in an offshore equipment installation phase of a wellhead platform project. Finally, the sensitivity analysis of the proposed robust model is performed considering different conservation levels, and the results are evaluated by Monte Carlo simulation with three normal, uniform and triangular distributions. The findings demonstrate that the robustness of the model against the variations of uncertain parameters.
A Robust Bi-objective Optimization Model for Resource Levelling Project Scheduling Problem with Discounted Cash Flows
KSCE J Civ Eng
Banihashemi, Sayyid Ali (author) / Khalilzadeh, Mohammad (author)
KSCE Journal of Civil Engineering ; 26 ; 2539-2554
2022-06-01
16 pages
Article (Journal)
Electronic Resource
English
Multi-mode project scheduling , Resource leveling , Net present value (NPV) , Robust optimization , Lexicographic Goal Programming (LGP) , Non-dominated sorting genetic , algorithm (NSGA-II) , Multi-objective particle swarm , optimization (MOPSO) Engineering , Civil Engineering , Industrial Pollution Prevention , Geotechnical Engineering & Applied Earth Sciences
British Library Online Contents | 2002
|Optimization of Project Time-Cost Trade-Off Problem with Discounted Cash Flows
British Library Online Contents | 2011
|Optimization of Project Time-Cost Trade-Off Problem with Discounted Cash Flows
Online Contents | 2011
|Bi-objective Optimization for Resource-constrained Robust Construction Project Scheduling
Springer Verlag | 2024
|