Pummersdorfer Tunnel – Water conditions in the shallow tunnel / Pummersdorfer Tunnel – Wasserverhältnisse im seicht liegenden Tunnel
The Westbahn line between Vienna and Wels in Austria is being upgraded to four tracks to improve its capacity and performance for passenger and goods traffic. The opening of the section “Gap‐closing St.Pölten‐Loosdorf (GZU)” in 2017 completed the four‐track Westbahn line between Vienna and Linz. The Pummersdorfer Tunnel is the last tunnel in this section and is designed as a single‐bore two‐track tunnel with a length of 3.5 km. The tunnel runs close to the surface with a maximum of 25 m overburden in weathered or unweathered Miocene schlier (marl). The driving of the tunnel encountered two groundwater horizons, pore groundwater in the Quaternary cover gravels above the tunnel crown and water in the joints of the Miocene schlier in or just above tunnel level. Some unexpected heavy water inrushes occurred during tunnelling.
The article first gives an overview of the project and the geological conditions and is then concerned with the effects of the groundwater inflows on the tunnelling works and the groundwater use in the near vicinity.
Für die Erhöhung der Kapazität und Leistungsfähigkeit im Personen‐ und Güterverkehr wird die Westbahn zwischen Wien und Wels viergleisig ausgebaut. Mit Inbetriebnahme des Abschnitts “Lückenschluss St.Pölten‐Loosdorf (GZU)” im Jahr 2017 wird die viergleisige Westbahn zwischen Wien‐ und Linz fertiggestellt. Der Tunnel Pummersdorf ist der letzte Tunnel in diesem Abschnitt und ist als einröhriger zweigleisiger Tunnel mit rund 3, 5 km Länge konzipiert. Der Tunnel verläuft oberflächennahe mit maximal 25 m Überlagerung im verwitterten bzw. unverwitterten Miozänschlier. Durch den Vortrieb sind zwei Grundwasserhorizonte, Porengrundwasser in den quartären Deckenschottern oberhalb der Tunnelfirste und Kluftgrundwasser im Miozänschlier in bzw. knapp über Tunnelniveau, berührt. Im Zuge des Vortriebs kam es kurzfristig zu unerwartet starken Wasserzutritten.
Der Beitrag gibt zunächst einen Überblick über das Projekt sowie die geologischen Rahmenbedingungen und befasst sich anschließend mit den Auswirkungen der Bergwasserzutritte für die Vortriebsarbeiten und die im Nahbereich befindlichen Grundwassernutzungen.
Pummersdorfer Tunnel – Water conditions in the shallow tunnel / Pummersdorfer Tunnel – Wasserverhältnisse im seicht liegenden Tunnel
The Westbahn line between Vienna and Wels in Austria is being upgraded to four tracks to improve its capacity and performance for passenger and goods traffic. The opening of the section “Gap‐closing St.Pölten‐Loosdorf (GZU)” in 2017 completed the four‐track Westbahn line between Vienna and Linz. The Pummersdorfer Tunnel is the last tunnel in this section and is designed as a single‐bore two‐track tunnel with a length of 3.5 km. The tunnel runs close to the surface with a maximum of 25 m overburden in weathered or unweathered Miocene schlier (marl). The driving of the tunnel encountered two groundwater horizons, pore groundwater in the Quaternary cover gravels above the tunnel crown and water in the joints of the Miocene schlier in or just above tunnel level. Some unexpected heavy water inrushes occurred during tunnelling.
The article first gives an overview of the project and the geological conditions and is then concerned with the effects of the groundwater inflows on the tunnelling works and the groundwater use in the near vicinity.
Für die Erhöhung der Kapazität und Leistungsfähigkeit im Personen‐ und Güterverkehr wird die Westbahn zwischen Wien und Wels viergleisig ausgebaut. Mit Inbetriebnahme des Abschnitts “Lückenschluss St.Pölten‐Loosdorf (GZU)” im Jahr 2017 wird die viergleisige Westbahn zwischen Wien‐ und Linz fertiggestellt. Der Tunnel Pummersdorf ist der letzte Tunnel in diesem Abschnitt und ist als einröhriger zweigleisiger Tunnel mit rund 3, 5 km Länge konzipiert. Der Tunnel verläuft oberflächennahe mit maximal 25 m Überlagerung im verwitterten bzw. unverwitterten Miozänschlier. Durch den Vortrieb sind zwei Grundwasserhorizonte, Porengrundwasser in den quartären Deckenschottern oberhalb der Tunnelfirste und Kluftgrundwasser im Miozänschlier in bzw. knapp über Tunnelniveau, berührt. Im Zuge des Vortriebs kam es kurzfristig zu unerwartet starken Wasserzutritten.
Der Beitrag gibt zunächst einen Überblick über das Projekt sowie die geologischen Rahmenbedingungen und befasst sich anschließend mit den Auswirkungen der Bergwasserzutritte für die Vortriebsarbeiten und die im Nahbereich befindlichen Grundwassernutzungen.
Pummersdorfer Tunnel – Water conditions in the shallow tunnel / Pummersdorfer Tunnel – Wasserverhältnisse im seicht liegenden Tunnel
Hödl, Reinhold (author) / Höllrigl, Michael (author)
Geomechanics and Tunnelling ; 7 ; 664-674
2014-12-01
11 pages
Article (Journal)
Electronic Resource
English
Pummersdorfer Tunnel – Water conditions in the shallow tunnel
Tema Archive | 2014
|Tunnel Face Stability Study in Soft Shallow Tunnel
Trans Tech Publications | 2014
|Parametric Study of Shallow Tunnel Under Seismic Conditions for Constantine Motorway Tunnel, Algeria
Online Contents | 2022
|Stability Analysis of 3D Tunnel Face of Shallow Rectangular Shield Tunnel
Springer Verlag | 2023
|Shed tunnel structure for shallow-buried bias tunnel and construction method
European Patent Office | 2020
|