Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
CONSTRUCTION METHOD FOR IMPERVIOUS CONCRETE FOR MBBR WATER TREATMENT PROCESS STRUCTURE
The present invention relates to the technical field of concrete construction, in particular to a construction method for impervious concrete for an MBBR water treatment process structure. By reasonably setting the quantity and position of embedded parts, the present invention may reduce the construction cost and ensure the construction quality at the same time; tapered heads and extension tie bars at both ends of an embedded tie bar may be disassembled and reused, thus further reducing the construction cost; and construction molding by continuous placing may not only meet the requirements of anti-seepage but also realize the tightening of construction formwork after concrete curing and formwork removal according to the set conditions, so as to ensure the construction to meet the requirements for surface degree and ensure the overall concrete quality after construction. SOlI: fabricating and installing reinforcements and installing inner and outer mounting frames outside the reinforcements Fig. S02:~ 3arctn osrcinfrwr n etn otmcntuto formork nd suportfrmoncioncnre.2ntaln tewl
CONSTRUCTION METHOD FOR IMPERVIOUS CONCRETE FOR MBBR WATER TREATMENT PROCESS STRUCTURE
The present invention relates to the technical field of concrete construction, in particular to a construction method for impervious concrete for an MBBR water treatment process structure. By reasonably setting the quantity and position of embedded parts, the present invention may reduce the construction cost and ensure the construction quality at the same time; tapered heads and extension tie bars at both ends of an embedded tie bar may be disassembled and reused, thus further reducing the construction cost; and construction molding by continuous placing may not only meet the requirements of anti-seepage but also realize the tightening of construction formwork after concrete curing and formwork removal according to the set conditions, so as to ensure the construction to meet the requirements for surface degree and ensure the overall concrete quality after construction. SOlI: fabricating and installing reinforcements and installing inner and outer mounting frames outside the reinforcements Fig. S02:~ 3arctn osrcinfrwr n etn otmcntuto formork nd suportfrmoncioncnre.2ntaln tewl
CONSTRUCTION METHOD FOR IMPERVIOUS CONCRETE FOR MBBR WATER TREATMENT PROCESS STRUCTURE
HAO DAN (Autor:in) / LIU JIAYIN (Autor:in) / ZHAO ZHI (Autor:in) / TANG JIANHE (Autor:in) / WANG ZHIYONG (Autor:in) / XI LIPING (Autor:in) / DENG CUNJUN (Autor:in) / CHEN KUI (Autor:in) / WANG ZHONGYI (Autor:in) / GONG SIKUN (Autor:in)
28.10.2021
Patent
Elektronische Ressource
Englisch
IPC:
E04H
Gebäude oder ähnliche Bauwerke für besondere Zwecke
,
BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES
/
C02F
Behandlung von Wasser, Schmutzwasser, Abwasser oder von Abwasserschlamm
,
TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
/
E02D
FOUNDATIONS
,
Gründungen
/
E04G
SCAFFOLDING
,
Baugerüste
Anti-seepage concrete construction method for MBBR water treatment process structure
Europäisches Patentamt | 2021
|Construction process of oversized impervious concrete pool
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2023
|COMMUNICATION PIPE UNIT, IMPERVIOUS STRUCTURE, AND IMPERVIOUS CONSTRUCTION METHOD
Europäisches Patentamt | 2016
|Europäisches Patentamt | 2024
|