The invention discloses a wading one-time pouring ornamental concrete retaining wall construction technology. The construction technology includes the steps that firstly, a foundation pit is compacted; secondly, a reinforced concrete foundation base is poured; thirdly, a reinforcement cage is bound; fourthly, a waterproof blanket is fixed; fifthly, concrete pouring is conducted; sixthly, ornamental face layer forming is conducted; and seventhly, ornamental face layer protection layer forming is conducted. By means of the retaining wall structure and the construction technology, an ornamental face layer and a wall body are formed through one-time pouring, the structural strength is high, the decoration effect is high, in addition, durability is high, and the construction technology is simple.
本发明公开了一种涉水一次性浇筑装饰混凝土挡土墙施工工艺,所述施工工艺包括:(1)夯实基坑,(2)浇筑钢筋混凝土基础基座,(3)绑扎钢筋笼,(4)固定防水毯,(5)浇筑混凝土,(6)装饰面层,(7)装饰面层保护层。根据本发明的涉水挡土墙结构及施工工艺,装饰面层与墙体主体采用一次性浇筑而成,结构强度高,装饰效果强并且耐久性高,施工工艺简单。
Wading one-time pouring ornamental concrete retaining wall construction technology
The invention discloses a wading one-time pouring ornamental concrete retaining wall construction technology. The construction technology includes the steps that firstly, a foundation pit is compacted; secondly, a reinforced concrete foundation base is poured; thirdly, a reinforcement cage is bound; fourthly, a waterproof blanket is fixed; fifthly, concrete pouring is conducted; sixthly, ornamental face layer forming is conducted; and seventhly, ornamental face layer protection layer forming is conducted. By means of the retaining wall structure and the construction technology, an ornamental face layer and a wall body are formed through one-time pouring, the structural strength is high, the decoration effect is high, in addition, durability is high, and the construction technology is simple.
本发明公开了一种涉水一次性浇筑装饰混凝土挡土墙施工工艺,所述施工工艺包括:(1)夯实基坑,(2)浇筑钢筋混凝土基础基座,(3)绑扎钢筋笼,(4)固定防水毯,(5)浇筑混凝土,(6)装饰面层,(7)装饰面层保护层。根据本发明的涉水挡土墙结构及施工工艺,装饰面层与墙体主体采用一次性浇筑而成,结构强度高,装饰效果强并且耐久性高,施工工艺简单。
Wading one-time pouring ornamental concrete retaining wall construction technology
一种涉水一次性浇筑装饰混凝土挡土墙施工工艺
LIU CHUNCAI (Autor:in) / JIA WEI (Autor:in) / WANG LIZHONG (Autor:in) / YUE WEI (Autor:in)
10.04.2020
Patent
Elektronische Ressource
Chinesisch
Construction method of gravity retaining wall under wading condition
Europäisches Patentamt | 2023
|Construction method for formwork lifting pouring of concrete retaining wall
Europäisches Patentamt | 2021
|Concrete retaining wall pouring formwork structure and construction method thereof