Pipe rack channel and construction method thereof
The invention relates to the technical field of building engineering, in particular to a pipe rack channel and a construction method thereof. The pipe rack channel comprises a bottom plate, side plates and a top plate. the construction method comprises the following steps of S1, early-stage preparation, S2, foundation pit excavation, S3, foundation pit bottom pretreatment, S4, bottom plate laying,S5, side plate installation, S6, top plate installation, and S7, waterproof treatment and earthwork backfilling. The pipe rack channel and the construction method thereof have the beneficial effectsthat during transporting, the bottom plate, the side plates and the top plate are transported to the construction position, transport is convenient, in addition, the bottom plate, the side plates andthe top plate are directly assembled together in the construction position, the assembling mode is convenient, and the time is saved.
本发明涉及建筑工程的技术领域,尤其是涉及一种管廊通道及其施工方法。该管廊通道包括底板、侧板与顶板,其施工方法包括一下步骤:S1:前期准备;S2:开挖基坑;S3:基坑底部预处理;S4:底板铺设;S5:侧板安装;S6:顶板安装;S7:防水处理以及土方回填。本发明具有以下有益效果:在运输时,分别将底板、侧板与顶板运输至施工位置,运输较为方便,而且在施工位置直接将其装配在一起,装配方式较为方便,节约时间。
Pipe rack channel and construction method thereof
The invention relates to the technical field of building engineering, in particular to a pipe rack channel and a construction method thereof. The pipe rack channel comprises a bottom plate, side plates and a top plate. the construction method comprises the following steps of S1, early-stage preparation, S2, foundation pit excavation, S3, foundation pit bottom pretreatment, S4, bottom plate laying,S5, side plate installation, S6, top plate installation, and S7, waterproof treatment and earthwork backfilling. The pipe rack channel and the construction method thereof have the beneficial effectsthat during transporting, the bottom plate, the side plates and the top plate are transported to the construction position, transport is convenient, in addition, the bottom plate, the side plates andthe top plate are directly assembled together in the construction position, the assembling mode is convenient, and the time is saved.
本发明涉及建筑工程的技术领域,尤其是涉及一种管廊通道及其施工方法。该管廊通道包括底板、侧板与顶板,其施工方法包括一下步骤:S1:前期准备;S2:开挖基坑;S3:基坑底部预处理;S4:底板铺设;S5:侧板安装;S6:顶板安装;S7:防水处理以及土方回填。本发明具有以下有益效果:在运输时,分别将底板、侧板与顶板运输至施工位置,运输较为方便,而且在施工位置直接将其装配在一起,装配方式较为方便,节约时间。
Pipe rack channel and construction method thereof
一种管廊通道及其施工方法
HUANG XINYUAN (Autor:in) / HUANG XIAOQIN (Autor:in) / HU HAIHUA (Autor:in) / HUANG YINGRUI (Autor:in) / HUANG BANGFENG (Autor:in)
21.04.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Combined template used for pipe rack construction and pipe rack construction method
Europäisches Patentamt | 2020
|Pile-holding guiding pipe rack and construction method thereof
Europäisches Patentamt | 2020
|Double-pipe-rack slip form trolley and double-pipe-rack construction method
Europäisches Patentamt | 2021
|