Special construction method for dragging main beam of extra-large bridge
The invention discloses a special construction method for a main beam of a lower dragging extra-large bridge, which comprises the following steps of: S02: 0 # section construction: pouring twice, andforming a support by once pouring; s03, hanging basket construction is conducted, specifically, a hanging basket is moved forwards to the front end of the zero beam section, and the formwork erectingelevation is determined; and erecting a formwork to bind the No.1 beam section steel bars and finish the arrangement of the prestressed pipeline. Aiming at the conditions that the span of a main beamis 200 m, the length of double cantilevers is large, the width-to-span ratio of a box girder is small, and the construction technical difficulty is large when the construction period goes through strong wind seasons and winter, smooth construction is guaranteed, and good practicability is achieved.
本发明公开了一种下拖特大桥主梁专项施工工法,包括步骤S02:0#段施工:分两次浇筑,托架按一次浇筑成型;步骤S03:挂篮施工:将挂篮前移至0号梁段前端,确定立模标高;立模绑扎1号梁段钢筋及完成预应力管道布置。针对主梁跨度200m,双悬臂长度长、箱梁宽跨比小、施工期经历大风季节和冬季的施工技术难度大情况,本发明保障了施工的顺利进行,具有较好的实用性。
Special construction method for dragging main beam of extra-large bridge
The invention discloses a special construction method for a main beam of a lower dragging extra-large bridge, which comprises the following steps of: S02: 0 # section construction: pouring twice, andforming a support by once pouring; s03, hanging basket construction is conducted, specifically, a hanging basket is moved forwards to the front end of the zero beam section, and the formwork erectingelevation is determined; and erecting a formwork to bind the No.1 beam section steel bars and finish the arrangement of the prestressed pipeline. Aiming at the conditions that the span of a main beamis 200 m, the length of double cantilevers is large, the width-to-span ratio of a box girder is small, and the construction technical difficulty is large when the construction period goes through strong wind seasons and winter, smooth construction is guaranteed, and good practicability is achieved.
本发明公开了一种下拖特大桥主梁专项施工工法,包括步骤S02:0#段施工:分两次浇筑,托架按一次浇筑成型;步骤S03:挂篮施工:将挂篮前移至0号梁段前端,确定立模标高;立模绑扎1号梁段钢筋及完成预应力管道布置。针对主梁跨度200m,双悬臂长度长、箱梁宽跨比小、施工期经历大风季节和冬季的施工技术难度大情况,本发明保障了施工的顺利进行,具有较好的实用性。
Special construction method for dragging main beam of extra-large bridge
下拖特大桥主梁专项施工工法
LIANG PENGGANG (Autor:in) / XU SHAOPING (Autor:in) / MA TIANCHANG (Autor:in) / CHANG YANHUA (Autor:in) / SU CHUNSHENG (Autor:in) / HAO YUFENG (Autor:in) / MENG FANWEI (Autor:in) / GUO WANHUI (Autor:in) / GUO JIANQIANG (Autor:in) / JIANG XINHE (Autor:in)
16.06.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Closure construction method for continuous rigid frame beam of lower dragging extra-large bridge
Europäisches Patentamt | 2020
|Bridge construction method and bridge dragging traction system
Europäisches Patentamt | 2021
|Steel truss bridge dragging construction device and construction method
Europäisches Patentamt | 2024
|Dragging and pushing construction method for large-span through steel truss bridge
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2023
|