Formwork mounting method
The invention discloses a formwork mounting method, which comprises the following steps of: snapping a line on a floor construction plane in a positioning manner; arranging a floor and beam formwork support body, reserving a working face when the formwork support body is arranged on a wall body so as to be used for wall body steel bar binding and later wall body formwork combining work, and binding wall body steel bars while arranging the formwork support body; laying the floor and beam formworks; after binding of the wall steel bars is completed, completing installation of the wall formwork;supplementing the floor formwork supports and the floor formworks which are not arranged near the wall body; completing reinforcing and adjusting of the formwork; and checking and accepting the formwork. Construction is more compact, the construction period is shortened, the wall steel bar binding environment is improved, and the construction cost is reduced.
本发明公开一种模板安装方法,包括以下步骤,将楼层施工平面定位弹线;布设楼板、梁支模架体,布设至墙体时留出工作面,以用于所述墙体绑扎钢筋以及后期所述墙体模板合模的工作,布设支模架体的同时,进行墙体钢筋绑扎;进行所述楼板、梁模板铺设;待所述墙体钢筋绑扎完成后,完成所述墙体模板的安装;补足所述墙体附近未布设的楼板支模架及所述楼板模板;完成模板的加固及调整;进行所述模板的验收;其使得施工更加紧凑,缩短施工工期,改善墙体钢筋绑扎环境,降低施工成本。
Formwork mounting method
The invention discloses a formwork mounting method, which comprises the following steps of: snapping a line on a floor construction plane in a positioning manner; arranging a floor and beam formwork support body, reserving a working face when the formwork support body is arranged on a wall body so as to be used for wall body steel bar binding and later wall body formwork combining work, and binding wall body steel bars while arranging the formwork support body; laying the floor and beam formworks; after binding of the wall steel bars is completed, completing installation of the wall formwork;supplementing the floor formwork supports and the floor formworks which are not arranged near the wall body; completing reinforcing and adjusting of the formwork; and checking and accepting the formwork. Construction is more compact, the construction period is shortened, the wall steel bar binding environment is improved, and the construction cost is reduced.
本发明公开一种模板安装方法,包括以下步骤,将楼层施工平面定位弹线;布设楼板、梁支模架体,布设至墙体时留出工作面,以用于所述墙体绑扎钢筋以及后期所述墙体模板合模的工作,布设支模架体的同时,进行墙体钢筋绑扎;进行所述楼板、梁模板铺设;待所述墙体钢筋绑扎完成后,完成所述墙体模板的安装;补足所述墙体附近未布设的楼板支模架及所述楼板模板;完成模板的加固及调整;进行所述模板的验收;其使得施工更加紧凑,缩短施工工期,改善墙体钢筋绑扎环境,降低施工成本。
Formwork mounting method
一种模板安装方法
XIAO PEILEI (Autor:in) / LIU YUTAO (Autor:in) / CHEN CHENG (Autor:in) / CHEN YONGWEI (Autor:in) / WANG ZUOTONG (Autor:in) / CHEN MO (Autor:in) / ZHAO SHUSHAN (Autor:in) / ZHAO ZONGYUAN (Autor:in) / WU SHUOJUN (Autor:in) / WANG JIAYU (Autor:in)
20.11.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Formwork column mounting construction structure and formwork column mounting construction method
Europäisches Patentamt | 2024
|Formwork system and formwork mounting and positioning method
Europäisches Patentamt | 2021
|Europäisches Patentamt | 2022
|Building formwork mounting device and mounting method thereof
Europäisches Patentamt | 2022
|