Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Roadbed filling construction method
The invention relates to the technical field of building construction, and discloses a roadbed filling construction method. The method comprises the following steps: step 1, roadbed lofting; step 2, site cleaning; step 3, compacting before filling; step 4, elevation measuring: measuring, detecting, recording and calculating the filling elevation of each layer of a compacted roadbed; step 5, fillerselecting: selecting and determining a roadbed filler; step 6, embankment feeding: carrying out layered filling treatment and paving leveling treatment on the roadbed to be fed, and carrying out filler water content detection on the roadbed subjected to watering and airing; step 7, leveling and compacting: performing layered static pressing and layered vibration pressing on the to-be-compacted roadbed according to designed filler compaction conditions to obtain a compacted roadbed; and step 8, finishing and maintaining: finishing and reinforcing a slope, a width, a height and flatness of an embankment slope and the roadbed of the compacted roadbed. Problems that an existing roadbed filling construction method is low in construction efficiency and high in construction cost are solved.
本发明涉及建筑施工技术领域,公开了一种路基填筑施工方法。该方法包括:步骤一、路基放样;步骤二、场地清理;步骤三、填前压实;步骤四、标高测量:对压实路基的每层填筑标高进行测量、检测记录和计算;步骤五、填料选择:选取并确定路基填料;步骤六、路堤上料:对待上料路基进行分层填筑处理和摊铺整平处理,对洒水晾晒后的路基进行填料含水量检测;步骤七、平整压实:按照设计的填料压实条件对待压实路基进行分层静压和分层振压得到压实后的路基;步骤八、修整养护:对压实后的路基的路堤边坡和路基进行坡度、宽度、高度和平整度的修整处理并进行加固处理。本发明解决了现有的路基填筑施工方法存在施工效率低和施工成本高的问题。
Roadbed filling construction method
The invention relates to the technical field of building construction, and discloses a roadbed filling construction method. The method comprises the following steps: step 1, roadbed lofting; step 2, site cleaning; step 3, compacting before filling; step 4, elevation measuring: measuring, detecting, recording and calculating the filling elevation of each layer of a compacted roadbed; step 5, fillerselecting: selecting and determining a roadbed filler; step 6, embankment feeding: carrying out layered filling treatment and paving leveling treatment on the roadbed to be fed, and carrying out filler water content detection on the roadbed subjected to watering and airing; step 7, leveling and compacting: performing layered static pressing and layered vibration pressing on the to-be-compacted roadbed according to designed filler compaction conditions to obtain a compacted roadbed; and step 8, finishing and maintaining: finishing and reinforcing a slope, a width, a height and flatness of an embankment slope and the roadbed of the compacted roadbed. Problems that an existing roadbed filling construction method is low in construction efficiency and high in construction cost are solved.
本发明涉及建筑施工技术领域,公开了一种路基填筑施工方法。该方法包括:步骤一、路基放样;步骤二、场地清理;步骤三、填前压实;步骤四、标高测量:对压实路基的每层填筑标高进行测量、检测记录和计算;步骤五、填料选择:选取并确定路基填料;步骤六、路堤上料:对待上料路基进行分层填筑处理和摊铺整平处理,对洒水晾晒后的路基进行填料含水量检测;步骤七、平整压实:按照设计的填料压实条件对待压实路基进行分层静压和分层振压得到压实后的路基;步骤八、修整养护:对压实后的路基的路堤边坡和路基进行坡度、宽度、高度和平整度的修整处理并进行加固处理。本发明解决了现有的路基填筑施工方法存在施工效率低和施工成本高的问题。
Roadbed filling construction method
路基填筑施工方法
XUE FENG (Autor:in) / LI YONGJUN (Autor:in) / LIU BAISEN (Autor:in) / FAN ZHONGHUAI (Autor:in) / ZHOU TONG (Autor:in)
27.11.2020
Patent
Elektronische Ressource
Chinesisch
Roadbed filling construction device and construction method
Europäisches Patentamt | 2024
|