Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Prefabricated assembled working well and assembling method thereof
The invention provides a prefabricated assembled working well and an assembling method thereof. The prefabricated assembled working well comprises a well body, a water collecting pit block, a connector block, a connector block assembling hole, a water collecting pit block assembling hole and a wellhead block. The assembling method of the prefabricated assembled working well comprises the steps that all the structures of the working well are split into a plurality of assembling blocks, then the split parts of the assembling blocks are determined on site according to construction conditions, andjoints between the assembling blocks and the assembling holes are connected and assembled together through bolts after sealing materials are added on site. According to the prefabricated assembled working well and the assembling method thereof, all the assembling blocks can be prefabricated in a factory, the efficiency is improved, industrial mass production can be achieved, the production cost is reduced, and the standardization degree is improved. In addition, the connector block is arranged to be the independent assembling block, and the construction condition that the height of an inlet wire outside the well is changed indefinitely is better adapted; and meanwhile, the connector block and the assembling holes are detachably connected, the connector block can be independently detachedand then replaced and updated under the condition that the well body is not affected, and the design life of the well body is fully played.
一种预制拼装工作井及其拼装方法,其中预制拼装工作井包括井体、集水坑块、接口块、接口块拼装孔、集水坑块拼装孔和井口块,预制拼装工作井的拼装方法包括将工作井的全部结构拆分为多个拼装块,然后在现场根据施工条件确定拼装块的拆分部位,拼装块与拼装孔之间的接缝现场加入密封材料后通过螺栓连接拼装在一起。本发明可以在工厂预制各拼装块,提高效率,可以工业化大批量生产降低生产成本,提高标准化程度。而且,本发明将接口块设置为单独的拼装块,更好适应井外进线高度变化不定的施工条件;同时接口块与拼装孔采用可拆卸的连接方式,接口块可在不影响井体的情况下单独拆卸后替换更新,充分发挥井体的设计寿命。
Prefabricated assembled working well and assembling method thereof
The invention provides a prefabricated assembled working well and an assembling method thereof. The prefabricated assembled working well comprises a well body, a water collecting pit block, a connector block, a connector block assembling hole, a water collecting pit block assembling hole and a wellhead block. The assembling method of the prefabricated assembled working well comprises the steps that all the structures of the working well are split into a plurality of assembling blocks, then the split parts of the assembling blocks are determined on site according to construction conditions, andjoints between the assembling blocks and the assembling holes are connected and assembled together through bolts after sealing materials are added on site. According to the prefabricated assembled working well and the assembling method thereof, all the assembling blocks can be prefabricated in a factory, the efficiency is improved, industrial mass production can be achieved, the production cost is reduced, and the standardization degree is improved. In addition, the connector block is arranged to be the independent assembling block, and the construction condition that the height of an inlet wire outside the well is changed indefinitely is better adapted; and meanwhile, the connector block and the assembling holes are detachably connected, the connector block can be independently detachedand then replaced and updated under the condition that the well body is not affected, and the design life of the well body is fully played.
一种预制拼装工作井及其拼装方法,其中预制拼装工作井包括井体、集水坑块、接口块、接口块拼装孔、集水坑块拼装孔和井口块,预制拼装工作井的拼装方法包括将工作井的全部结构拆分为多个拼装块,然后在现场根据施工条件确定拼装块的拆分部位,拼装块与拼装孔之间的接缝现场加入密封材料后通过螺栓连接拼装在一起。本发明可以在工厂预制各拼装块,提高效率,可以工业化大批量生产降低生产成本,提高标准化程度。而且,本发明将接口块设置为单独的拼装块,更好适应井外进线高度变化不定的施工条件;同时接口块与拼装孔采用可拆卸的连接方式,接口块可在不影响井体的情况下单独拆卸后替换更新,充分发挥井体的设计寿命。
Prefabricated assembled working well and assembling method thereof
预制拼装工作井及其拼装方法
XIAO RAN (Autor:in) / LU WEIDONG (Autor:in) / LI XIAOLIN (Autor:in) / ZHU DONGNIAN (Autor:in) / ZHANG YU (Autor:in) / LIU WENBO (Autor:in) / XU DONG (Autor:in) / LI YATAO (Autor:in) / CHAI JIAN (Autor:in) / ZHANG XUETAO (Autor:in)
04.12.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Prefabricated assembled pier and assembling method thereof
Europäisches Patentamt | 2020
|Prefabricated inspection well and assembling method thereof
Europäisches Patentamt | 2022
|Prefabricated assembled inspection well and construction method thereof
Europäisches Patentamt | 2020
|Fully-assembled prefabricated column-steel beam connecting joint and assembling method thereof
Europäisches Patentamt | 2024
|