Aqueduct Bailey beam design and construction method
The invention relates to the field of building construction, in particular to an aqueduct Bailey beam design and construction method. A bent frame with the height smaller than 10 m is a single bent frame, a bent frame with the height larger than 10 m is a double-bent frame structure, and the maximum bent frame height is 19.83 m. Considering that a covering layer in an aqueduct position is thick, mostly is sludge or loess, the bearing capacity is low and the treatment difficulty is large, according to previous similar engineering construction success experience, a 30# aqueduct of a project is located in a V-shaped ditch, the topographic condition is complex, the maximum bent frame height is 19.83 m, a steel cylinder pile Bailey beam is adopted as a formwork for supporting in aqueduct body construction, and a set-shaped steel formwork is adopted as a formwork.
本发明涉及建筑施工领域,具体涉及一种渡槽贝雷梁设计施工方法,排架高度小于10m为单排架,排架高度大于10m为双排架结构,最大排架高度19.83米。考虑到渡槽位置覆盖层较厚,多为淤泥或黄土,承载力较低,处理难度大,根据以往类似工程施工成功经验,本工程30#渡槽位于V型沟,地形条件较为复杂,最大排架高度19.83米,槽身施工采用钢筒桩贝雷梁作为模板支撑,模板采用定型钢模板。
Aqueduct Bailey beam design and construction method
The invention relates to the field of building construction, in particular to an aqueduct Bailey beam design and construction method. A bent frame with the height smaller than 10 m is a single bent frame, a bent frame with the height larger than 10 m is a double-bent frame structure, and the maximum bent frame height is 19.83 m. Considering that a covering layer in an aqueduct position is thick, mostly is sludge or loess, the bearing capacity is low and the treatment difficulty is large, according to previous similar engineering construction success experience, a 30# aqueduct of a project is located in a V-shaped ditch, the topographic condition is complex, the maximum bent frame height is 19.83 m, a steel cylinder pile Bailey beam is adopted as a formwork for supporting in aqueduct body construction, and a set-shaped steel formwork is adopted as a formwork.
本发明涉及建筑施工领域,具体涉及一种渡槽贝雷梁设计施工方法,排架高度小于10m为单排架,排架高度大于10m为双排架结构,最大排架高度19.83米。考虑到渡槽位置覆盖层较厚,多为淤泥或黄土,承载力较低,处理难度大,根据以往类似工程施工成功经验,本工程30#渡槽位于V型沟,地形条件较为复杂,最大排架高度19.83米,槽身施工采用钢筒桩贝雷梁作为模板支撑,模板采用定型钢模板。
Aqueduct Bailey beam design and construction method
一种渡槽贝雷梁设计施工方法
LI HAINING (Autor:in) / GUO YANHUI (Autor:in) / WANG LIMIN (Autor:in) / ZHAO XIN (Autor:in) / DU XILONG (Autor:in) / QI YOUXIN (Autor:in) / SUN XINJIAN (Autor:in) / LIAN YAOJIE (Autor:in)
07.05.2021
Patent
Elektronische Ressource
Chinesisch
Aqueduct formwork supporting system supported on bailey beam and construction method
Europäisches Patentamt | 2020
|Fabricated arched aqueduct support, aqueduct and construction method of aqueduct support
Europäisches Patentamt | 2024
|Movable aqueduct making machine and aqueduct construction method
Europäisches Patentamt | 2023
|Aqueduct structure and construction method for reinforcing partial aqueduct sections
Europäisches Patentamt | 2024
|