Aerated block drilling and pipe arranging construction technology
The invention provides an aerated block drilling and pipe arranging construction technology, and belongs to the technical field of building construction. The aerated block drilling and pipe arranging construction technology comprises the following steps that S1, deep design is carried out, specifically, a detailed brick arrangement drawing and a pipeline and wire box positioning arrangement drawing are provided; S2, centralized construction is carried out, specifically, according to the brick arrangement drawing and the pipeline and wire box positioning arrangement drawing, hole forming machining is carried out on building blocks; S3, paying off of building bodies is carried out, specifically, a building body construction control line, an electric box horizontal center position line, an electric box horizontal side line and the like are popped up; S4, water and electricity pipelines are installed; S5, brick arranging and positioning are carried out, specifically, the mortar joint width between the bricks is adjusted according to the brick arranging drawing and the pipeline and wire box positioning arrangement drawing; and S6, brick casing pipe matching is carried out, specifically, according to the building body width, the water and electricity pipeline specification and the pipeline number, a building block middle drilling casing pipe is adopted. According to the aerated block drilling and pipe arranging construction technology, holes are directly formed in the building body bricks for pipe distribution, so that hollowing and cracking of the wall body caused by reduction of the cutting slotting problem are avoided, the construction quality is improved, the working efficiency is effectively improved, and the investment is reduced.
本申请提供了加气块钻孔布管施工工艺,属于建筑施工技术领域。该加气块钻孔布管施工工艺,包括如下步骤:S1:深化设计:出具详细排砖图及管线、线盒定位布置图;S2:集中施工:依据排砖图及管线、线盒定位布置图,对砌块进行开孔加工;S3:砌体放线:弹出砌体施工控制线、电盒水平中心位置线、电箱水平边线等;S4:水电管线安装;S5:排砖定位:依据排砖图及管线、线盒定位布置图,调整砖和砖之间的灰缝宽度;S6:配砖套管:根据砌体宽度、水电管线规格及管线数量,采用砌块中间钻孔套管。在本申请中通过在砌体砖上直接取孔布管,避免减少切割开槽的问题导致墙体空鼓开裂,提高施工质量,有效提高工作效率,降低投入。
Aerated block drilling and pipe arranging construction technology
The invention provides an aerated block drilling and pipe arranging construction technology, and belongs to the technical field of building construction. The aerated block drilling and pipe arranging construction technology comprises the following steps that S1, deep design is carried out, specifically, a detailed brick arrangement drawing and a pipeline and wire box positioning arrangement drawing are provided; S2, centralized construction is carried out, specifically, according to the brick arrangement drawing and the pipeline and wire box positioning arrangement drawing, hole forming machining is carried out on building blocks; S3, paying off of building bodies is carried out, specifically, a building body construction control line, an electric box horizontal center position line, an electric box horizontal side line and the like are popped up; S4, water and electricity pipelines are installed; S5, brick arranging and positioning are carried out, specifically, the mortar joint width between the bricks is adjusted according to the brick arranging drawing and the pipeline and wire box positioning arrangement drawing; and S6, brick casing pipe matching is carried out, specifically, according to the building body width, the water and electricity pipeline specification and the pipeline number, a building block middle drilling casing pipe is adopted. According to the aerated block drilling and pipe arranging construction technology, holes are directly formed in the building body bricks for pipe distribution, so that hollowing and cracking of the wall body caused by reduction of the cutting slotting problem are avoided, the construction quality is improved, the working efficiency is effectively improved, and the investment is reduced.
本申请提供了加气块钻孔布管施工工艺,属于建筑施工技术领域。该加气块钻孔布管施工工艺,包括如下步骤:S1:深化设计:出具详细排砖图及管线、线盒定位布置图;S2:集中施工:依据排砖图及管线、线盒定位布置图,对砌块进行开孔加工;S3:砌体放线:弹出砌体施工控制线、电盒水平中心位置线、电箱水平边线等;S4:水电管线安装;S5:排砖定位:依据排砖图及管线、线盒定位布置图,调整砖和砖之间的灰缝宽度;S6:配砖套管:根据砌体宽度、水电管线规格及管线数量,采用砌块中间钻孔套管。在本申请中通过在砌体砖上直接取孔布管,避免减少切割开槽的问题导致墙体空鼓开裂,提高施工质量,有效提高工作效率,降低投入。
Aerated block drilling and pipe arranging construction technology
加气块钻孔布管施工工艺
YU YAPING (Autor:in) / ZHANG JIANPENG (Autor:in) / DUAN YANLIN (Autor:in) / PENG JINGXIANG (Autor:in) / CHEN XIANGCHAO (Autor:in) / TIAN KANG (Autor:in) / WANG ZHENXING (Autor:in) / GONG LIN (Autor:in) / LIU GUOQING (Autor:in) / WANG WEIXIN (Autor:in)
13.07.2021
Patent
Elektronische Ressource
Chinesisch
Aerated concrete block guniting plastering construction method
Europäisches Patentamt | 2021
|Improved autoclaved aerated concrete block processing technology
Europäisches Patentamt | 2021
|Autoclaved aerated concrete block and construction method thereof