Method for excavating foundation pit in water-rich sand layer
The invention discloses a method for excavating a foundation pit in a water-rich sand layer. The method is characterized by including the steps that step one, water leakage of an underground diaphragm wall is detected; step two, geological radar scanning is carried out, and cavities at the bottom are prevented; step three, a steel plate is blocked at a weak underground diaphragm wall joint position, and the weak position of a wall joint is prevented from spewing; step four, high-pressure jet grouting piles are adopted at the joint positions of the underground diaphragm walls for wall joint water stopping; step five, WSS grouting reinforcement is conducted on the joints of the underground diaphragm walls with risks in the excavation process; step six, a draining and pressure-reducing dewatering well is additionally arranged outside the pit; step seven, a support is erected in time, slope excavation is carried out, and a slotting and crack detection system is strictly executed; and step eight, field construction monitoring is enhanced, and foundation pit excavation is guided through monitoring data.
一种富水砂层中基坑开挖方法,其特征在于,包括如下步骤:步骤一、地连墙渗漏水检测;步骤二、进行地质雷达扫描,预防底部存在空洞;步骤三、在薄弱的地连墙接缝位置封堵钢板,避免墙缝薄弱位置发生喷涌;步骤四、地连墙接缝位置采用高压旋喷桩进行墙缝止水;步骤五、开挖过程中有风险的地连墙接缝处WSS注浆加固补强;步骤六、坑外增设疏干兼降压降水井;步骤七、及时架设支撑,进行放坡开挖,严格执行掏槽检缝制度;步骤八、加强现场施工监测,通过监测数据指导基坑开挖。
Method for excavating foundation pit in water-rich sand layer
The invention discloses a method for excavating a foundation pit in a water-rich sand layer. The method is characterized by including the steps that step one, water leakage of an underground diaphragm wall is detected; step two, geological radar scanning is carried out, and cavities at the bottom are prevented; step three, a steel plate is blocked at a weak underground diaphragm wall joint position, and the weak position of a wall joint is prevented from spewing; step four, high-pressure jet grouting piles are adopted at the joint positions of the underground diaphragm walls for wall joint water stopping; step five, WSS grouting reinforcement is conducted on the joints of the underground diaphragm walls with risks in the excavation process; step six, a draining and pressure-reducing dewatering well is additionally arranged outside the pit; step seven, a support is erected in time, slope excavation is carried out, and a slotting and crack detection system is strictly executed; and step eight, field construction monitoring is enhanced, and foundation pit excavation is guided through monitoring data.
一种富水砂层中基坑开挖方法,其特征在于,包括如下步骤:步骤一、地连墙渗漏水检测;步骤二、进行地质雷达扫描,预防底部存在空洞;步骤三、在薄弱的地连墙接缝位置封堵钢板,避免墙缝薄弱位置发生喷涌;步骤四、地连墙接缝位置采用高压旋喷桩进行墙缝止水;步骤五、开挖过程中有风险的地连墙接缝处WSS注浆加固补强;步骤六、坑外增设疏干兼降压降水井;步骤七、及时架设支撑,进行放坡开挖,严格执行掏槽检缝制度;步骤八、加强现场施工监测,通过监测数据指导基坑开挖。
Method for excavating foundation pit in water-rich sand layer
一种富水砂层中基坑开挖方法
CHEN DONG (Autor:in) / XIANG LONGSHENG (Autor:in) / GAO SHUNYU (Autor:in) / CEN LIHUI (Autor:in) / WANG ZHENLONG (Autor:in) / HU XUEYU (Autor:in) / LI CHONG (Autor:in)
12.11.2021
Patent
Elektronische Ressource
Chinesisch
Method for controlling quality of rotary excavating pile under water-rich sand layer condition
Europäisches Patentamt | 2015
|Excavating system of deep foundation pit and excavating construction method of deep foundation pit
Europäisches Patentamt | 2022
|