Method for pouring comprehensive pipe gallery in limited space of urban dense area
The invention discloses a method for pouring a comprehensive pipe gallery in a limited space of an urban dense area. The method comprises the following steps of constructing foundation pit supporting piles; pouring and constructing concrete slabs outside the foundation pit sideline; installing and constructing the concrete pump pipe at the foundation pit sideline; mounting and constructing the guide rails on the concrete slab; installing and constructing the gantry crane, wherein the gantry crane can be installed on the guide rails in a walking mode along the guide rails; transporting the construction materials into the construction section of the foundation pit through a gantry crane; installing the moving device on the guide rail in a walking mode along the guide rail, and installing the material distributing machine on the moving device; pulling the moving device to the pouring site of the construction section by the gantry crane, then connecting the concrete pump pipe to the material distributing machine, then the material distributing machine is adopted for pouring till pouring at the pouring site is completed, and the steps are repeated till pouring of all the construction sections is completed. According to the construction method, the distributing machine can move along the foundation pit for pouring, and the problem that the urban dense area limited space comprehensive pipe gallery is difficult to pour is solved.
本申请公开了一种城市密集区受限空间综合管廊浇筑方法,包括以下步骤:基坑支护桩施工。基坑边线外的混凝土板浇筑施工。基坑边线处的混凝土泵管安装施工。混凝土板上的导轨安装施工。龙门吊安装施工,其中,龙门吊可沿导轨行走地安装在导轨上。采用龙门吊将施工材料运输至基坑的施工段内。将移动装置可沿导轨行走地安装在导轨上,将布料机安装在移动装置上。采用龙门吊牵引移动装置至施工段的浇筑地点处,然后将混凝土泵管连接至布料机,接着采用布料机进行浇筑,直至浇筑地点处浇筑完成,重复上述步骤,直至全部施工段浇筑完成。本申请的施工方法使得布料机可沿基坑移动浇筑,解决城区密集区受限空间综合管廊浇筑困难的问题。
Method for pouring comprehensive pipe gallery in limited space of urban dense area
The invention discloses a method for pouring a comprehensive pipe gallery in a limited space of an urban dense area. The method comprises the following steps of constructing foundation pit supporting piles; pouring and constructing concrete slabs outside the foundation pit sideline; installing and constructing the concrete pump pipe at the foundation pit sideline; mounting and constructing the guide rails on the concrete slab; installing and constructing the gantry crane, wherein the gantry crane can be installed on the guide rails in a walking mode along the guide rails; transporting the construction materials into the construction section of the foundation pit through a gantry crane; installing the moving device on the guide rail in a walking mode along the guide rail, and installing the material distributing machine on the moving device; pulling the moving device to the pouring site of the construction section by the gantry crane, then connecting the concrete pump pipe to the material distributing machine, then the material distributing machine is adopted for pouring till pouring at the pouring site is completed, and the steps are repeated till pouring of all the construction sections is completed. According to the construction method, the distributing machine can move along the foundation pit for pouring, and the problem that the urban dense area limited space comprehensive pipe gallery is difficult to pour is solved.
本申请公开了一种城市密集区受限空间综合管廊浇筑方法,包括以下步骤:基坑支护桩施工。基坑边线外的混凝土板浇筑施工。基坑边线处的混凝土泵管安装施工。混凝土板上的导轨安装施工。龙门吊安装施工,其中,龙门吊可沿导轨行走地安装在导轨上。采用龙门吊将施工材料运输至基坑的施工段内。将移动装置可沿导轨行走地安装在导轨上,将布料机安装在移动装置上。采用龙门吊牵引移动装置至施工段的浇筑地点处,然后将混凝土泵管连接至布料机,接着采用布料机进行浇筑,直至浇筑地点处浇筑完成,重复上述步骤,直至全部施工段浇筑完成。本申请的施工方法使得布料机可沿基坑移动浇筑,解决城区密集区受限空间综合管廊浇筑困难的问题。
Method for pouring comprehensive pipe gallery in limited space of urban dense area
一种城市密集区受限空间综合管廊浇筑方法
LIN XISEN (Autor:in) / GONG JUNSONG (Autor:in) / WANG LINFENG (Autor:in) / LIU FANGYUAN (Autor:in) / XU ZHIBAO (Autor:in) / WANG YU (Autor:in)
11.02.2022
Patent
Elektronische Ressource
Chinesisch
Underground comprehensive pipe gallery pouring formwork system
Europäisches Patentamt | 2021
|Pouring and mounting method of comprehensive pipe gallery