Construction method for steel pipe pile of intelligent lamp pole foundation of municipal road
The invention provides a municipal road intelligent lamp pole foundation steel pipe pile construction method which comprises the steps that a twist drill is installed through a crawler photovoltaic pile driver for drilling, and a pile hole is formed; hoisting the steel pipe pile into the pile hole through a truck crane; after the steel pipe pile enters the pile hole, the perpendicularity of the steel pipe pile is corrected according to preset requirements; the steel pipe pile is installed through a crawler photovoltaic pile driver and a vibratory hammer pile driver; and filling yellow sand into the steel pipe pile, and carrying out pile top treatment. According to the method, the influence of crossing and collision of municipal engineering pipelines can be effectively solved, construction is rapid, meanwhile, construction safety and construction quality are improved, the construction period is shortened, later foundation treatment is eradicated, and cost is saved.
本发明提供一种市政道路智慧灯杆基础钢管桩施工方法,包括:通过履带光伏打桩机安装螺旋钻进行钻孔,形成桩孔;通过汽车吊将钢管桩吊装至桩孔内;钢管桩进入桩孔后,根据预设要求校正所述钢管桩的垂直度;通过履带光伏打桩机和振动锤打桩机进行钢管桩安装;在钢管桩内灌黄沙填实,进行桩顶处理。本发明能够有效解决市政工程管线交叉碰撞影响,快速施工,同时提高了施工安全性和施工质量、缩短了施工工期,杜绝了后期基础处理,节约了成本。
Construction method for steel pipe pile of intelligent lamp pole foundation of municipal road
The invention provides a municipal road intelligent lamp pole foundation steel pipe pile construction method which comprises the steps that a twist drill is installed through a crawler photovoltaic pile driver for drilling, and a pile hole is formed; hoisting the steel pipe pile into the pile hole through a truck crane; after the steel pipe pile enters the pile hole, the perpendicularity of the steel pipe pile is corrected according to preset requirements; the steel pipe pile is installed through a crawler photovoltaic pile driver and a vibratory hammer pile driver; and filling yellow sand into the steel pipe pile, and carrying out pile top treatment. According to the method, the influence of crossing and collision of municipal engineering pipelines can be effectively solved, construction is rapid, meanwhile, construction safety and construction quality are improved, the construction period is shortened, later foundation treatment is eradicated, and cost is saved.
本发明提供一种市政道路智慧灯杆基础钢管桩施工方法,包括:通过履带光伏打桩机安装螺旋钻进行钻孔,形成桩孔;通过汽车吊将钢管桩吊装至桩孔内;钢管桩进入桩孔后,根据预设要求校正所述钢管桩的垂直度;通过履带光伏打桩机和振动锤打桩机进行钢管桩安装;在钢管桩内灌黄沙填实,进行桩顶处理。本发明能够有效解决市政工程管线交叉碰撞影响,快速施工,同时提高了施工安全性和施工质量、缩短了施工工期,杜绝了后期基础处理,节约了成本。
Construction method for steel pipe pile of intelligent lamp pole foundation of municipal road
一种市政道路智慧灯杆基础钢管桩施工方法
TANG ZEJUN (Autor:in) / LI JING (Autor:in) / BAI DERONG (Autor:in) / LI ZHENGHONG (Autor:in) / ZENG HONGCHAO (Autor:in) / LIU LIKUAN (Autor:in) / JIANG YAN (Autor:in)
01.03.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Pile foundation of intelligent lamp pole and installation method thereof
Europäisches Patentamt | 2021
|CONSTRUCTION METHOD OF STEEL PIPE PILE, AND STEEL PIPE PILE FOUNDATION
Europäisches Patentamt | 2024
|CONSTRUCTION METHOD OF STEEL PIPE PILE AND STEEL PIPE PILE FOUNDATION