Inverted conical shell water tower construction process
The invention relates to the technical field of building construction, in particular to an inverted conical shell water tower construction technology which comprises the following steps that firstly, an inverted conical shell water tower is measured and positioned; secondly, a supporting cylinder structure is constructed; and thirdly, the inverted conical shell water tank structure is constructed. The method has the advantages that the suspender adopts a steel strand, one-time investment and repeated use are achieved, a hydraulic jack is adopted for lifting, mechanical operation is adopted for oil supply and oil return, the number of constructors used in an old process is only 1/2, meanwhile, cutting and transporting work of the suspender of the high steel ring beam is reduced, and potential safety hazards of construction are reduced; besides, according to the slip form technology, the center hole jack ascends and resets to the height of the next stroke, oil supply is balanced, a plummet does not need to be adopted for centering, alignment and alignment in each stroke, time is saved for next-step construction, the construction period can be shortened, and the construction period of an old technology can be shortened by 1/3 through supporting cylinder construction.
本发明涉及建筑施工技术领域,尤其涉及一种倒锥壳水塔施工工艺,括以下步骤:步骤一、倒锥壳水塔测量定位;步骤二、支筒结构施工;步骤三、倒锥壳水箱结构施工。本发明的优点是:吊杆采用钢绞线,一次性投入,反复使用,提升采用液压千斤顶,采用机械操作供油和回油,所用施工人员只有旧工艺所用施工人员的1/2,同时,减少高钢环梁的吊杆的切割及运输工作,减少了施工安全隐患;另外,的滑模工艺,通过穿心式千斤顶上升复位到下一行程高度,供油均衡,每一个行程都不用采用线坠对中、找正,找正,节省时间进行下一步施工,可缩短工期,支筒施工可缩短旧工艺所用工期的1/3时间。
Inverted conical shell water tower construction process
The invention relates to the technical field of building construction, in particular to an inverted conical shell water tower construction technology which comprises the following steps that firstly, an inverted conical shell water tower is measured and positioned; secondly, a supporting cylinder structure is constructed; and thirdly, the inverted conical shell water tank structure is constructed. The method has the advantages that the suspender adopts a steel strand, one-time investment and repeated use are achieved, a hydraulic jack is adopted for lifting, mechanical operation is adopted for oil supply and oil return, the number of constructors used in an old process is only 1/2, meanwhile, cutting and transporting work of the suspender of the high steel ring beam is reduced, and potential safety hazards of construction are reduced; besides, according to the slip form technology, the center hole jack ascends and resets to the height of the next stroke, oil supply is balanced, a plummet does not need to be adopted for centering, alignment and alignment in each stroke, time is saved for next-step construction, the construction period can be shortened, and the construction period of an old technology can be shortened by 1/3 through supporting cylinder construction.
本发明涉及建筑施工技术领域,尤其涉及一种倒锥壳水塔施工工艺,括以下步骤:步骤一、倒锥壳水塔测量定位;步骤二、支筒结构施工;步骤三、倒锥壳水箱结构施工。本发明的优点是:吊杆采用钢绞线,一次性投入,反复使用,提升采用液压千斤顶,采用机械操作供油和回油,所用施工人员只有旧工艺所用施工人员的1/2,同时,减少高钢环梁的吊杆的切割及运输工作,减少了施工安全隐患;另外,的滑模工艺,通过穿心式千斤顶上升复位到下一行程高度,供油均衡,每一个行程都不用采用线坠对中、找正,找正,节省时间进行下一步施工,可缩短工期,支筒施工可缩短旧工艺所用工期的1/3时间。
Inverted conical shell water tower construction process
一种倒锥壳水塔施工工艺
WANG ZHANJUN (Autor:in) / WU DEBIN (Autor:in) / ZHANG RUI (Autor:in)
12.04.2022
Patent
Elektronische Ressource
Chinesisch
Construction method of adjustable bracket for inverted conical shell water tower construction
Europäisches Patentamt | 2022
|Water tank cast-in-site method of inverted conical shell water tower cable-stayed formwork in air
Europäisches Patentamt | 2015
|Inverted conical funnel supporting system and construction method
Europäisches Patentamt | 2024
|Large standing tower inverted installation device and inverted construction method
Europäisches Patentamt | 2020
|Construction method of large-gradient inverted conical funnel-shaped top plate
Europäisches Patentamt | 2023
|