Synchronous displacement construction method for power transmission angle steel tower
The invention discloses a synchronous displacement construction method for a power transmission angle steel tower. The synchronous displacement construction method comprises the following steps that S1, a connecting beam and a new base are poured; s2, tower legs of the angle steel tower are integrally fixed, and an angle steel tower body is reinforced; s3, a stay wire system, a jacking system, a traction system, a braking system and a sliding system are installed; and S4, the angle steel tower is moved and fixed to the new base, and movement of the angle steel tower is completed. According to the method, the processes of dismantling and assembling the power transmission angle steel tower can be omitted, the working intensity of workers is reduced, the high-altitude operation time is shortened, the personal safety of the workers is guaranteed, the construction efficiency is improved, and the purpose of recycling resources is achieved.
本发明公开了一种输电角钢塔同步位移施工方法,包括如下步骤:S1、连接梁以及新基座浇筑;S2、对角钢塔塔腿整体固定,并对角钢塔本体进行加固;S3、安装拉线系统、顶升系统、牵引系统、制动系统以及滑动系统;S4、对角钢塔移动,并且固定在新基座上,完成对角钢塔的移动。本发明能够减免了输电角钢塔拆除、组装的流程,降低了工作人员的工作强度,减少了高空作业时间,保证了工作人员的人身安全,提高了施工效率,达到了资源重复利用的目的。
Synchronous displacement construction method for power transmission angle steel tower
The invention discloses a synchronous displacement construction method for a power transmission angle steel tower. The synchronous displacement construction method comprises the following steps that S1, a connecting beam and a new base are poured; s2, tower legs of the angle steel tower are integrally fixed, and an angle steel tower body is reinforced; s3, a stay wire system, a jacking system, a traction system, a braking system and a sliding system are installed; and S4, the angle steel tower is moved and fixed to the new base, and movement of the angle steel tower is completed. According to the method, the processes of dismantling and assembling the power transmission angle steel tower can be omitted, the working intensity of workers is reduced, the high-altitude operation time is shortened, the personal safety of the workers is guaranteed, the construction efficiency is improved, and the purpose of recycling resources is achieved.
本发明公开了一种输电角钢塔同步位移施工方法,包括如下步骤:S1、连接梁以及新基座浇筑;S2、对角钢塔塔腿整体固定,并对角钢塔本体进行加固;S3、安装拉线系统、顶升系统、牵引系统、制动系统以及滑动系统;S4、对角钢塔移动,并且固定在新基座上,完成对角钢塔的移动。本发明能够减免了输电角钢塔拆除、组装的流程,降低了工作人员的工作强度,减少了高空作业时间,保证了工作人员的人身安全,提高了施工效率,达到了资源重复利用的目的。
Synchronous displacement construction method for power transmission angle steel tower
一种输电角钢塔同步位移施工方法
WANG CHUNLIN (Autor:in) / JIN YIKUI (Autor:in) / HAN XUEWEN (Autor:in) / LV BO (Autor:in) / ZHANG JUN (Autor:in) / QI YONGCHENG (Autor:in) / WANG YONGJUN (Autor:in) / BAI HAILONG (Autor:in) / DENG JIEYING (Autor:in) / ZHANG XIAOLONG (Autor:in)
07.06.2022
Patent
Elektronische Ressource
Chinesisch
Power transmission tower angle steel reinforcing device and power transmission tower
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2021
|Power transmission tower angle steel connection joint
Europäisches Patentamt | 2015
|