Construction process for dynamic compaction replacement
The invention relates to the technical field of building construction, and discloses a construction process for dynamic compaction replacement, which comprises the following steps of: setting a working area and a safety range, isolating by using a baffle plate, and dispatching a specially-assigned person for guarding to prevent irrelevant personnel from entering; various sundries on the construction site are cleaned, and the construction site is leveled, so that the construction site meets the construction requirements; the whole construction site is measured, the site elevation is measured again, tamping points are arranged through a steel ruler according to a construction drawing, and the positions of the tamping points are marked and numbered; and the dynamic compaction machine is in place, and a rammer is aligned with a ramming point. According to the construction technology for dynamic compaction replacement, through pre-cleaning and leveling of the construction site, impurities can be prevented from being mixed in, the quality is improved, reinforcing raw materials are saved, the strength and deformation resistance of a sludge soft underlying layer are improved, the liquefaction possibility of liquefiable sand in the site is eliminated, the construction technology is simple, the applicable soil texture range is wide, and the construction cost is low. The bearing capacity and the deformation modulus of the foundation are improved, and the foundation is greatly reinforced.
本发明涉及建筑施工技术领域,且公开了一种强夯置换的施工工艺,包括以下步骤:设置工作区域及安全范围,使用挡板隔离并派专人值守,防止无关人员进入;清理施工场地的各种杂物,并整平施工场地,使施工场地满足施工要求;对整个施工场地进行测量,复测场地标高,用钢尺按施工图布置夯点并对夯点位置进行标记并编号;强夯机械就位,将夯锤对准夯点。该强夯置换的施工工艺,通过对施工场地的预清理和整平,能够防止杂物混入,提高了质量,节省加固原材料,提高供淤泥质软弱下卧层的强度和抗变形能力,消除本场地可液化砂土液化可能,施工工艺简单,适用土质范围广,提高了地基承载能力及变形模量,大大加固了地基。
Construction process for dynamic compaction replacement
The invention relates to the technical field of building construction, and discloses a construction process for dynamic compaction replacement, which comprises the following steps of: setting a working area and a safety range, isolating by using a baffle plate, and dispatching a specially-assigned person for guarding to prevent irrelevant personnel from entering; various sundries on the construction site are cleaned, and the construction site is leveled, so that the construction site meets the construction requirements; the whole construction site is measured, the site elevation is measured again, tamping points are arranged through a steel ruler according to a construction drawing, and the positions of the tamping points are marked and numbered; and the dynamic compaction machine is in place, and a rammer is aligned with a ramming point. According to the construction technology for dynamic compaction replacement, through pre-cleaning and leveling of the construction site, impurities can be prevented from being mixed in, the quality is improved, reinforcing raw materials are saved, the strength and deformation resistance of a sludge soft underlying layer are improved, the liquefaction possibility of liquefiable sand in the site is eliminated, the construction technology is simple, the applicable soil texture range is wide, and the construction cost is low. The bearing capacity and the deformation modulus of the foundation are improved, and the foundation is greatly reinforced.
本发明涉及建筑施工技术领域,且公开了一种强夯置换的施工工艺,包括以下步骤:设置工作区域及安全范围,使用挡板隔离并派专人值守,防止无关人员进入;清理施工场地的各种杂物,并整平施工场地,使施工场地满足施工要求;对整个施工场地进行测量,复测场地标高,用钢尺按施工图布置夯点并对夯点位置进行标记并编号;强夯机械就位,将夯锤对准夯点。该强夯置换的施工工艺,通过对施工场地的预清理和整平,能够防止杂物混入,提高了质量,节省加固原材料,提高供淤泥质软弱下卧层的强度和抗变形能力,消除本场地可液化砂土液化可能,施工工艺简单,适用土质范围广,提高了地基承载能力及变形模量,大大加固了地基。
Construction process for dynamic compaction replacement
一种强夯置换的施工工艺
XIAO LIN (Autor:in) / HUANG WENPING (Autor:in) / WANG YANG (Autor:in) / YANG FAN (Autor:in) / YANG QUNRONG (Autor:in)
15.07.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction process and equipment for dynamic compaction replacement
Europäisches Patentamt | 2021
|Europäisches Patentamt | 2016
|Feeding dynamic compaction replacement composite construction method
Europäisches Patentamt | 2023
|GRID COMPACTION PLATE FOR PERRFORMING DYNAMIC REPLACEMENT CONSTRUCTION METHOD
Europäisches Patentamt | 2025