Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Construction method for reinforcing foundation pit of overpass rail transit
The invention relates to the technical field of upper-span rail transit foundation pit reinforcement construction, in particular to an upper-span rail transit foundation pit reinforcement construction method, which adopts a mode of combining MJS construction method piles and three-shaft mixing piles to greatly improve the construction speed and control the deformation of an existing subway tunnel within an allowable range. After construction parameters of the three-axis stirring piles and the MJS construction method piles are determined through experiments, foundation pit reinforcement construction is started, the three-axis stirring piles are constructed firstly for foundation pit reinforcement of the overpass rail transit, and then the MJS construction method piles are constructed after the three-axis stirring piles reach certain strength.
本发明涉及上跨轨道交通基坑加固施工的技术领域,特别是涉及一种上跨轨道交通基坑加固施工方法,其采用MJS工法桩和三轴搅拌桩相结合的方式能大大提高施工速度,同时控制既有地铁隧道变形在允许范围内;通过实验确定三轴搅拌桩及MJS工法桩施工参数后,开始基坑加固施工,上跨轨道交通基坑加固先施工三轴搅拌桩,待三轴搅拌桩达到一定强度后,再施工MJS工法桩。
Construction method for reinforcing foundation pit of overpass rail transit
The invention relates to the technical field of upper-span rail transit foundation pit reinforcement construction, in particular to an upper-span rail transit foundation pit reinforcement construction method, which adopts a mode of combining MJS construction method piles and three-shaft mixing piles to greatly improve the construction speed and control the deformation of an existing subway tunnel within an allowable range. After construction parameters of the three-axis stirring piles and the MJS construction method piles are determined through experiments, foundation pit reinforcement construction is started, the three-axis stirring piles are constructed firstly for foundation pit reinforcement of the overpass rail transit, and then the MJS construction method piles are constructed after the three-axis stirring piles reach certain strength.
本发明涉及上跨轨道交通基坑加固施工的技术领域,特别是涉及一种上跨轨道交通基坑加固施工方法,其采用MJS工法桩和三轴搅拌桩相结合的方式能大大提高施工速度,同时控制既有地铁隧道变形在允许范围内;通过实验确定三轴搅拌桩及MJS工法桩施工参数后,开始基坑加固施工,上跨轨道交通基坑加固先施工三轴搅拌桩,待三轴搅拌桩达到一定强度后,再施工MJS工法桩。
Construction method for reinforcing foundation pit of overpass rail transit
一种上跨轨道交通基坑加固施工方法
CHENG FANGCHENG (Autor:in) / ZHOU GUO (Autor:in) / ZHAO SHUAIPEI (Autor:in) / SUN SIXIN (Autor:in) / WANG ZHONGSHENG (Autor:in)
15.07.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Upper-span rail transit foundation pit reinforcing device
Europäisches Patentamt | 2024
|Reinforcing method of existing operating railway overpass
Europäisches Patentamt | 2022
|Urban overpass pile foundation underpinning pre-jacking construction method
Europäisches Patentamt | 2022
|Construction method for protecting overpass structure around deep foundation pits
Europäisches Patentamt | 2021
|Construction method for dismantling overpass bridge of overpass railway
Europäisches Patentamt | 2024
|