Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Integral lifting construction method for steel structure lifting roof
The invention discloses an integral lifting construction method for a steel structure lifting roof. The integral lifting construction method comprises the following steps: step 1, reinforcing a support; 2, overall construction of the steel structure; 3, a lifting system is installed; 3.1, upper and lower lifting points are installed and lifted; step 3.2, mounting a steel strand and a hydraulic system; 3.3, controlling connection of a power line; 4, vertical guide rails are arranged; 5, trying to lift; step 5.1, fixing in place and pre-tightening the steel strand; step 5.2, lifting, grading and loading; step 5.3, carrying out structure off-ground inspection; step 5.4, attitude detection and adjustment; step 5.5, dismantling the temporary supporting facility; step 6, formal lifting; seventhly, a telescopic connecting system is installed; 8, linkage debugging of the lifting system; and 9, officially using. According to the method, the lifting weight, span and area are not limited, and the method is suitable for lifting various complex environment structures.
一种钢结构升降屋面整体提升施工方法,包括有以下步骤:步骤1支座加固;步骤2钢结构整体施工;步骤3安装提升系统;步骤3.1安装提升上下吊点;步骤3.2钢绞线及液压系统的安装;步骤3.3控制、动力线的连接;步骤4设置竖向导轨;步骤5试提升;步骤5.1固定就位与钢绞线预紧;步骤5.2提升分级加载;步骤5.3结构离地检查;步骤5.4姿态检测调整;步骤5.5临时支撑设施拆除;步骤6正式提升;步骤7伸缩连接系统安装;步骤8提升系统联动调试;步骤9正式使用。该方法提升重量、跨度、面积不受限制,适用于各种复杂环境结构的提升。
Integral lifting construction method for steel structure lifting roof
The invention discloses an integral lifting construction method for a steel structure lifting roof. The integral lifting construction method comprises the following steps: step 1, reinforcing a support; 2, overall construction of the steel structure; 3, a lifting system is installed; 3.1, upper and lower lifting points are installed and lifted; step 3.2, mounting a steel strand and a hydraulic system; 3.3, controlling connection of a power line; 4, vertical guide rails are arranged; 5, trying to lift; step 5.1, fixing in place and pre-tightening the steel strand; step 5.2, lifting, grading and loading; step 5.3, carrying out structure off-ground inspection; step 5.4, attitude detection and adjustment; step 5.5, dismantling the temporary supporting facility; step 6, formal lifting; seventhly, a telescopic connecting system is installed; 8, linkage debugging of the lifting system; and 9, officially using. According to the method, the lifting weight, span and area are not limited, and the method is suitable for lifting various complex environment structures.
一种钢结构升降屋面整体提升施工方法,包括有以下步骤:步骤1支座加固;步骤2钢结构整体施工;步骤3安装提升系统;步骤3.1安装提升上下吊点;步骤3.2钢绞线及液压系统的安装;步骤3.3控制、动力线的连接;步骤4设置竖向导轨;步骤5试提升;步骤5.1固定就位与钢绞线预紧;步骤5.2提升分级加载;步骤5.3结构离地检查;步骤5.4姿态检测调整;步骤5.5临时支撑设施拆除;步骤6正式提升;步骤7伸缩连接系统安装;步骤8提升系统联动调试;步骤9正式使用。该方法提升重量、跨度、面积不受限制,适用于各种复杂环境结构的提升。
Integral lifting construction method for steel structure lifting roof
一种钢结构升降屋面整体提升施工方法
WANG ZHEN (Autor:in) / LI FENGBO (Autor:in) / FAN ZHAOXU (Autor:in) / LIU PENG (Autor:in) / LI MENGMENG (Autor:in) / LUO APENG (Autor:in) / GAO JIANWEN (Autor:in) / ZHANG SHANFENG (Autor:in) / LIU MEIYUAN (Autor:in) / SHA BINGLEI (Autor:in)
20.01.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Europäisches Patentamt | 2020
|Integral lifting construction method for large-span net rack roof structure
Europäisches Patentamt | 2020
|Engineering Index Backfile | 1954
|Lifting and sliding device for steel structure roof construction
Europäisches Patentamt | 2023
|