Construction method of prefabricated concrete building prefabricated outer wall abutted seam drainage pipe
The invention relates to an assembly type concrete building prefabricated outer wall abutted seam drainage pipe construction method which comprises the following steps that firstly, the flatness condition of a wall needs to be confirmed before construction, and a needed abutted seam is cleaned so as to prevent the situation that the waterproof effect becomes poor due to foreign matter residues in the seam; secondly, the abutted seam is filled with liner materials, masking paper is pasted to the portions, on the two sides of the abutted seam, of the wall body, the lower liner material is arranged in an inclined inverted-L shape, the upper liner material is arranged in a vertical shape, and a flow guide pipe needed for drainage is arranged in a gap between the liner materials and tightly attached to the liner materials; 3, glue needed to be used is mixed and stirred to be uniform and then placed in glue distribution equipment, glue distribution is carried out on the abutted seams from bottom to top through the glue distribution equipment, and in the glue distribution process, the glue distribution equipment can also carry out trowelling treatment on the glue till glue distribution is completed; and 4, after the tape glue is hardened, the masking paper is torn off, and the wall is cleaned.
本发明涉及一种装配式混凝土建筑预制外墙拼缝排水管施工方法,包括以下步骤:步骤一:施工前需确认墙体平整度情况,并对所需拼缝进行清理,以防止缝隙中的异物残留导致防水效果变差;步骤二:向拼缝内填入衬垫材料,并在拼缝两侧的墙体上粘贴美纹纸,位于下方的衬垫材料呈倾斜倒L状设置,位于上方的衬垫材料呈竖直状设置,将排水所需的导流管置于衬垫材料之间的空隙,并与衬垫材料紧密贴合;步骤三:将所需使用的胶水混合搅拌均匀后,置于布胶设备内,并通过所述布胶设备从下往上对拼缝进行布胶,布胶过程中,所述布胶设备还可对胶水进行抹平处理,直至布胶完成;步骤四:带胶水硬化后,撕去美纹纸,并对墙体进行清洁处理。
Construction method of prefabricated concrete building prefabricated outer wall abutted seam drainage pipe
The invention relates to an assembly type concrete building prefabricated outer wall abutted seam drainage pipe construction method which comprises the following steps that firstly, the flatness condition of a wall needs to be confirmed before construction, and a needed abutted seam is cleaned so as to prevent the situation that the waterproof effect becomes poor due to foreign matter residues in the seam; secondly, the abutted seam is filled with liner materials, masking paper is pasted to the portions, on the two sides of the abutted seam, of the wall body, the lower liner material is arranged in an inclined inverted-L shape, the upper liner material is arranged in a vertical shape, and a flow guide pipe needed for drainage is arranged in a gap between the liner materials and tightly attached to the liner materials; 3, glue needed to be used is mixed and stirred to be uniform and then placed in glue distribution equipment, glue distribution is carried out on the abutted seams from bottom to top through the glue distribution equipment, and in the glue distribution process, the glue distribution equipment can also carry out trowelling treatment on the glue till glue distribution is completed; and 4, after the tape glue is hardened, the masking paper is torn off, and the wall is cleaned.
本发明涉及一种装配式混凝土建筑预制外墙拼缝排水管施工方法,包括以下步骤:步骤一:施工前需确认墙体平整度情况,并对所需拼缝进行清理,以防止缝隙中的异物残留导致防水效果变差;步骤二:向拼缝内填入衬垫材料,并在拼缝两侧的墙体上粘贴美纹纸,位于下方的衬垫材料呈倾斜倒L状设置,位于上方的衬垫材料呈竖直状设置,将排水所需的导流管置于衬垫材料之间的空隙,并与衬垫材料紧密贴合;步骤三:将所需使用的胶水混合搅拌均匀后,置于布胶设备内,并通过所述布胶设备从下往上对拼缝进行布胶,布胶过程中,所述布胶设备还可对胶水进行抹平处理,直至布胶完成;步骤四:带胶水硬化后,撕去美纹纸,并对墙体进行清洁处理。
Construction method of prefabricated concrete building prefabricated outer wall abutted seam drainage pipe
一种装配式混凝土建筑预制外墙拼缝排水管施工方法
TIAN PANYIN (Autor:in) / ZHAO YAJUN (Autor:in) / ZHENG YUJIN (Autor:in) / ZHANG YUNTING (Autor:in)
03.03.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS
/
B05D
PROCESSES FOR APPLYING LIQUIDS OR OTHER FLUENT MATERIALS TO SURFACES, IN GENERAL
,
Verfahren zum Aufbringen von Flüssigkeiten oder von anderen fließfähigen Stoffen auf Oberflächen allgemein
/
E04G
SCAFFOLDING
,
Baugerüste
Prefabricated element abutted seam waterproof structure
Europäisches Patentamt | 2021
|Prefabricated overhanging eave plate abutted seam construction structure and construction method
Europäisches Patentamt | 2024
|Prefabricated building laminated slab abutted seam mortar leakage prevention structure
Europäisches Patentamt | 2021
|Construction device for drainage pipe at abutted seam of assembled outer wall
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2020
|