The invention discloses a cross-sea bridge main tower optimization reinforcement construction process which comprises the steps that a to-be-reinforced structure in a bridge main tower is obtained, and a reinforcement construction scheme suitable for the to-be-reinforced structure is formulated; and based on the construction scheme, corresponding reinforcing construction is conducted on the to-be-reinforced structure, and the reinforced bridge main tower is obtained. The invention belongs to the field of cross-sea bridge main tower construction, a reinforcing construction scheme suitable for a to-be-reinforced structure is formulated through the to-be-reinforced structure in a bridge main tower in combination with the actual situation of a construction site, and corresponding reinforcing construction is performed on the to-be-reinforced structure based on the reinforcing construction scheme, so that the stability of the bridge main tower is enhanced.
本申请公开了一种跨海大桥主塔优化补强施工工艺,所述跨海大桥主塔优化补强施工工艺包括:获取桥梁主塔中的待补强结构,并制定适用于所述待补强结构的补强施工方案;基于所述施工方案,对所述待补强结构进行相应的补强施工,得到补强后的桥梁主塔。本申请属于跨海大桥主塔施工领域,通过桥梁主塔中的待补强结构,结合施工现场的实际情况,制定适用于所述待补强结构的补强施工方案,基于所述补强施工方案,对所述待补强结构进行相应的补强施工,以此加强桥梁主塔的稳定性。
Optimized reinforcing construction process for main tower of cross-sea bridge
The invention discloses a cross-sea bridge main tower optimization reinforcement construction process which comprises the steps that a to-be-reinforced structure in a bridge main tower is obtained, and a reinforcement construction scheme suitable for the to-be-reinforced structure is formulated; and based on the construction scheme, corresponding reinforcing construction is conducted on the to-be-reinforced structure, and the reinforced bridge main tower is obtained. The invention belongs to the field of cross-sea bridge main tower construction, a reinforcing construction scheme suitable for a to-be-reinforced structure is formulated through the to-be-reinforced structure in a bridge main tower in combination with the actual situation of a construction site, and corresponding reinforcing construction is performed on the to-be-reinforced structure based on the reinforcing construction scheme, so that the stability of the bridge main tower is enhanced.
本申请公开了一种跨海大桥主塔优化补强施工工艺,所述跨海大桥主塔优化补强施工工艺包括:获取桥梁主塔中的待补强结构,并制定适用于所述待补强结构的补强施工方案;基于所述施工方案,对所述待补强结构进行相应的补强施工,得到补强后的桥梁主塔。本申请属于跨海大桥主塔施工领域,通过桥梁主塔中的待补强结构,结合施工现场的实际情况,制定适用于所述待补强结构的补强施工方案,基于所述补强施工方案,对所述待补强结构进行相应的补强施工,以此加强桥梁主塔的稳定性。
Optimized reinforcing construction process for main tower of cross-sea bridge
跨海大桥主塔优化补强施工工艺
LI DONG (Autor:in) / FENG LONG (Autor:in) / HE WENJIAN (Autor:in) / ZOU JINLONG (Autor:in) / CHEN QIANG (Autor:in) / YANG XIAO (Autor:in) / SHI XINPENG (Autor:in) / YANG FENGSHANG (Autor:in)
28.03.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Europäisches Patentamt | 2023
|Reinforcing construction method for top surface of lower cross beam of main tower
Europäisches Patentamt | 2023
|Main longitudinal beam reinforcing structure for bridge construction
Europäisches Patentamt | 2020
|