Construction method of cover and excavation top-down permanent steel pipe column
The invention relates to the technical field of steel pipe column construction, after pouring of cast-in-place pile concrete is completed, a steel pipe column can be hoisted into a pile casing, the steel pipe column is downwards inserted through an adjusting driving mechanism, the perpendicularity and the pile position deviation are checked and adjusted, and then the steel pipe column can be fixed to the top end of a cast-in-place pile; the steel pipe column does not need to be installed after condensation of the cast-in-place pile is completed, installation of the steel pipe column is simpler and more convenient, and the construction period of the steel pipe column is conveniently shortened.
本申请涉及钢管柱施工的技术领域,本申请在浇筑完灌注桩混凝土后,便可将钢管柱吊入至护筒内,经由调节驱动机构对钢管柱进行下插并校核调整垂直度与桩位偏差后便可实现钢管柱固定在灌注桩顶端,无需等待灌注桩凝结完成后再进行钢管柱的安装,使得钢管柱的安装更加简单方便,便于减少钢管柱的施工工期。
Construction method of cover and excavation top-down permanent steel pipe column
The invention relates to the technical field of steel pipe column construction, after pouring of cast-in-place pile concrete is completed, a steel pipe column can be hoisted into a pile casing, the steel pipe column is downwards inserted through an adjusting driving mechanism, the perpendicularity and the pile position deviation are checked and adjusted, and then the steel pipe column can be fixed to the top end of a cast-in-place pile; the steel pipe column does not need to be installed after condensation of the cast-in-place pile is completed, installation of the steel pipe column is simpler and more convenient, and the construction period of the steel pipe column is conveniently shortened.
本申请涉及钢管柱施工的技术领域,本申请在浇筑完灌注桩混凝土后,便可将钢管柱吊入至护筒内,经由调节驱动机构对钢管柱进行下插并校核调整垂直度与桩位偏差后便可实现钢管柱固定在灌注桩顶端,无需等待灌注桩凝结完成后再进行钢管柱的安装,使得钢管柱的安装更加简单方便,便于减少钢管柱的施工工期。
Construction method of cover and excavation top-down permanent steel pipe column
一种盖挖逆作永久钢管柱的施工方法
WU DONG (Autor:in) / ZHU ZHENHUA (Autor:in) / LIU XIAOTAO (Autor:in) / GUO JILU (Autor:in) / LU KAI (Autor:in) / WANG BAICHENG (Autor:in) / WANG JIEJUN (Autor:in) / LI XINYUN (Autor:in) / FANG ZISHAN (Autor:in) / GONG WENBO (Autor:in)
23.05.2023
Patent
Elektronische Ressource
Chinesisch
Construction method of cover-excavation top-down permanent steel pipe column
Europäisches Patentamt | 2020
|Europäisches Patentamt | 2022
|Europäisches Patentamt | 2023
|Cover-excavation top-down V column structure and construction method thereof
Europäisches Patentamt | 2022
|Europäisches Patentamt | 2022
|