Power transmission line tower settlement monitoring, early warning and protection device and method
The invention relates to a power transmission line tower settlement monitoring, early warning and protection device and method. The telescopic connecting rods are connected between the spiral supporting columns and the corner piles on the periphery of the power transmission line tower, and tension is provided for the corner piles on the periphery when settlement of the power transmission line tower exceeds an early warning value. Settlement monitoring equipment and settlement early warning equipment are arranged at the upper end of the spiral supporting column; the four corners of the bottom of the power transmission line tower body are connected with settlement monitoring equipment through cross rods. The tops of the four corner piles are flush with the tops of the spiral supporting columns. The settlement early warning equipment is used for converting spring pressure, caused by settlement, in the settlement monitoring equipment into charges to be output, amplifying charge signals, converting the charge signals into digital signals and transmitting the digital signals to the far-end receiving equipment; the far-end receiving equipment receives the digital signal transmitted by the signal transmitting equipment, then carries out data processing and judges whether the digital signal exceeds a settlement early warning value or not; real-time monitoring, early warning and protection of settlement of the power transmission line tower are achieved, and the safety problem caused by excessive settlement of the power transmission line tower is effectively reduced.
本发明涉及一种输电线塔沉降监测、预警和防护装置及方法。本发明将可伸缩连接杆连接于螺旋支撑柱与输电线塔的四周角桩之间,在输电线塔沉降超过预警值时为四周角桩提供拉力。所述螺旋支撑柱上端设有沉降监测设备及沉降预警设置;输电线塔塔身底部四角通过横杆与沉降监测设备连接,四个角桩桩顶与螺旋支撑柱顶部平齐;所述沉降预警设备用于将沉降引起的沉降监测设备中弹簧压力转化为电荷输出,并通过对电荷信号的放大及转换成数字信号后,发射至远端接收设备;远端接收设备接受信号发射设备传递的数字信号后进行数据处理并判断是否超出沉降预警值;实现对输电线塔沉降的实时监测、预警及防护,有效的减少因输电线塔过度沉降引发的安全问题。
Power transmission line tower settlement monitoring, early warning and protection device and method
The invention relates to a power transmission line tower settlement monitoring, early warning and protection device and method. The telescopic connecting rods are connected between the spiral supporting columns and the corner piles on the periphery of the power transmission line tower, and tension is provided for the corner piles on the periphery when settlement of the power transmission line tower exceeds an early warning value. Settlement monitoring equipment and settlement early warning equipment are arranged at the upper end of the spiral supporting column; the four corners of the bottom of the power transmission line tower body are connected with settlement monitoring equipment through cross rods. The tops of the four corner piles are flush with the tops of the spiral supporting columns. The settlement early warning equipment is used for converting spring pressure, caused by settlement, in the settlement monitoring equipment into charges to be output, amplifying charge signals, converting the charge signals into digital signals and transmitting the digital signals to the far-end receiving equipment; the far-end receiving equipment receives the digital signal transmitted by the signal transmitting equipment, then carries out data processing and judges whether the digital signal exceeds a settlement early warning value or not; real-time monitoring, early warning and protection of settlement of the power transmission line tower are achieved, and the safety problem caused by excessive settlement of the power transmission line tower is effectively reduced.
本发明涉及一种输电线塔沉降监测、预警和防护装置及方法。本发明将可伸缩连接杆连接于螺旋支撑柱与输电线塔的四周角桩之间,在输电线塔沉降超过预警值时为四周角桩提供拉力。所述螺旋支撑柱上端设有沉降监测设备及沉降预警设置;输电线塔塔身底部四角通过横杆与沉降监测设备连接,四个角桩桩顶与螺旋支撑柱顶部平齐;所述沉降预警设备用于将沉降引起的沉降监测设备中弹簧压力转化为电荷输出,并通过对电荷信号的放大及转换成数字信号后,发射至远端接收设备;远端接收设备接受信号发射设备传递的数字信号后进行数据处理并判断是否超出沉降预警值;实现对输电线塔沉降的实时监测、预警及防护,有效的减少因输电线塔过度沉降引发的安全问题。
Power transmission line tower settlement monitoring, early warning and protection device and method
一种输电线塔沉降监测、预警和防护装置及方法
CHEN QINGWEI (Autor:in) / WANG ZHIPENG (Autor:in) / XIE DAN (Autor:in) / ZHU YI (Autor:in) / XU JINKUN (Autor:in) / WANG DEXIANG (Autor:in) / ZHANG ZHAOHUAN (Autor:in) / TENG CHI (Autor:in) / WANG WENYANG (Autor:in) / ZHAO ZHIPENG (Autor:in)
23.05.2023
Patent
Elektronische Ressource
Chinesisch
Protection and monitoring early warning device for power transmission tower on slope
Europäisches Patentamt | 2020
|Power transmission tower settlement correction method
Europäisches Patentamt | 2023
|Differential settlement adjusting equipment for power transmission line tower footing
Europäisches Patentamt | 2023
|Electric power tower warning device with protection function
Europäisches Patentamt | 2021