Steel frame structure building wall AAC plate construction method and hoisting equipment
The invention relates to the field of steel frame structure building construction, in particular to a steel frame structure building wall AAC board construction method which comprises the following steps that firstly, building main body construction is conducted, specifically, building construction is conducted on a building main body according to a design drawing; secondly, AAC plates are pre-arranged in place, and before a top plate of a building construction layer is not installed and sealed, the AAC plates are hoisted to the construction layer and placed on a bottom plate of the construction layer; 3, fireproof construction of the steel mounting layer structure: arranging a fireproof layer on the steel structure of the building after the top of the steel structure of the building is sealed, or arranging a fireproof layer on the steel structure of the floor below the construction layer during building construction; and step 4, AAC plate installation: in an installation layer on which steel structure fireproof construction has been carried out, the AAC plate on the bottom plate is erected from the floor and then is installed at a wall body design position.
本发明涉及钢框架结构建筑施工领域,特别是涉及一种钢框架结构建筑墙体AAC板施工方法,包括以下步骤:步骤一建筑主体施工,首先按照设计图纸对建筑主体进行搭建施工;步骤二AAC板预就位,在建筑施工层的顶板尚未安装封闭前,将AAC板吊装到施工层,放置在施工层的底板上;步骤三钢安装层结构防火施工,建筑钢结构封顶之后对建筑的钢结构设置防火层,或者在建筑施工时对施工层下方楼层的钢结构上设置防火层;步骤四AAC板安装,在已经做好钢结构防火施工的安装层,从楼层内将底板上的AAC板起竖然后将AAC板安装到墙体设计位置。
Steel frame structure building wall AAC plate construction method and hoisting equipment
The invention relates to the field of steel frame structure building construction, in particular to a steel frame structure building wall AAC board construction method which comprises the following steps that firstly, building main body construction is conducted, specifically, building construction is conducted on a building main body according to a design drawing; secondly, AAC plates are pre-arranged in place, and before a top plate of a building construction layer is not installed and sealed, the AAC plates are hoisted to the construction layer and placed on a bottom plate of the construction layer; 3, fireproof construction of the steel mounting layer structure: arranging a fireproof layer on the steel structure of the building after the top of the steel structure of the building is sealed, or arranging a fireproof layer on the steel structure of the floor below the construction layer during building construction; and step 4, AAC plate installation: in an installation layer on which steel structure fireproof construction has been carried out, the AAC plate on the bottom plate is erected from the floor and then is installed at a wall body design position.
本发明涉及钢框架结构建筑施工领域,特别是涉及一种钢框架结构建筑墙体AAC板施工方法,包括以下步骤:步骤一建筑主体施工,首先按照设计图纸对建筑主体进行搭建施工;步骤二AAC板预就位,在建筑施工层的顶板尚未安装封闭前,将AAC板吊装到施工层,放置在施工层的底板上;步骤三钢安装层结构防火施工,建筑钢结构封顶之后对建筑的钢结构设置防火层,或者在建筑施工时对施工层下方楼层的钢结构上设置防火层;步骤四AAC板安装,在已经做好钢结构防火施工的安装层,从楼层内将底板上的AAC板起竖然后将AAC板安装到墙体设计位置。
Steel frame structure building wall AAC plate construction method and hoisting equipment
一种钢框架结构建筑墙体AAC板施工方法及起重设备
QIAN CHENG (Autor:in) / JIA JIANYING (Autor:in) / FENG MIN (Autor:in) / PENG QIBING (Autor:in) / WANG LIANLI (Autor:in) / SUN QI (Autor:in) / HAN LIWEI (Autor:in) / ZHANG QIUSHENG (Autor:in) / QU SIQI (Autor:in)
30.05.2023
Patent
Elektronische Ressource
Chinesisch
Steel plate hoisting method for building construction
Europäisches Patentamt | 2021
|Steel structure hoisting equipment for green building construction
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2020
|Large-span steel structure hoisting equipment for building construction
Europäisches Patentamt | 2024
|Large-span steel structure frame construction auxiliary hoisting equipment for stadium construction
Europäisches Patentamt | 2024
|