The invention provides a chimney rollover construction method, which belongs to the technical field of chimney rollover construction, and comprises the following steps: firstly, carrying out chimney foundation construction to form a chimney foundation cylinder body with a preset height; secondly, a hydraulic lifting rollover system is installed on the chimney cylinder body with the preset height, a supporting rod embedded in the reinforced concrete cylinder wall serves as a bearing force body, and the hydraulic lifting system climbs to drive an operation platform system; and then the installed hydraulic lifting formwork overturning system is lifted to the specified construction height, formwork installation and concrete pouring are conducted, and construction is conducted circularly according to the procedures till the chimney cylinder wall is poured. According to the method, the chimney formwork turnover construction efficiency can be improved, the construction cost is reduced, the overall appearance quality of chimney concrete is guaranteed, drilling safety of constructors is guaranteed, and the construction safety is improved.
本发明提供一种烟囱翻模施工方法,属于烟囱翻模施工技术领域,包括以下步骤:先进行烟囱基础施工以形成预设高度的烟囱基础筒身;然后在预设高度的烟囱筒身上安装液压提升翻模系统,以埋设于钢筋混凝土筒壁内的支撑杆为承载力主体,通过液压提升系统爬升带动操作平台系统;接着将安装好的液压提升翻模系统提升到规定的施工高度,进行模板的安装并浇筑混凝土,按照上述工序循环施工直至烟囱筒壁浇筑完成。本发明能够提高烟囱翻模施工效率,降低施工成本,保证整体的烟囱混凝土外观质量,保障施工人员安钻,提高施工的安全性。
Chimney rollover construction method
The invention provides a chimney rollover construction method, which belongs to the technical field of chimney rollover construction, and comprises the following steps: firstly, carrying out chimney foundation construction to form a chimney foundation cylinder body with a preset height; secondly, a hydraulic lifting rollover system is installed on the chimney cylinder body with the preset height, a supporting rod embedded in the reinforced concrete cylinder wall serves as a bearing force body, and the hydraulic lifting system climbs to drive an operation platform system; and then the installed hydraulic lifting formwork overturning system is lifted to the specified construction height, formwork installation and concrete pouring are conducted, and construction is conducted circularly according to the procedures till the chimney cylinder wall is poured. According to the method, the chimney formwork turnover construction efficiency can be improved, the construction cost is reduced, the overall appearance quality of chimney concrete is guaranteed, drilling safety of constructors is guaranteed, and the construction safety is improved.
本发明提供一种烟囱翻模施工方法,属于烟囱翻模施工技术领域,包括以下步骤:先进行烟囱基础施工以形成预设高度的烟囱基础筒身;然后在预设高度的烟囱筒身上安装液压提升翻模系统,以埋设于钢筋混凝土筒壁内的支撑杆为承载力主体,通过液压提升系统爬升带动操作平台系统;接着将安装好的液压提升翻模系统提升到规定的施工高度,进行模板的安装并浇筑混凝土,按照上述工序循环施工直至烟囱筒壁浇筑完成。本发明能够提高烟囱翻模施工效率,降低施工成本,保证整体的烟囱混凝土外观质量,保障施工人员安钻,提高施工的安全性。
Chimney rollover construction method
一种烟囱翻模施工方法
CHEN SIYAN (Autor:in) / ZHANG XU (Autor:in) / JIANG KONGRONG (Autor:in) / WU GUOHUA (Autor:in)
08.08.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Chimney rollover construction operation platform and device
Europäisches Patentamt | 2023
|Operating platform and chimney cylinder wall rollover construction method
Europäisches Patentamt | 2023
|Chimney cylinder rollover construction equipment with ear chambers and sightseeing function
Europäisches Patentamt | 2023
|Chimney rollover construction method with structural refractory bricks serving as inner mold
Europäisches Patentamt | 2023
|