Step-shaped net rack relay lifting suspension point conversion method
The invention discloses a step-shaped net rack relay lifting suspension point conversion method, which comprises the following steps of: assembling high-area net rack units, and arranging and installing a high-area net rack lifting assembly and a high-area net rack temporary lifting assembly; lifting the high-area net rack unit to a designed assembly height required by the low-area net rack unit by using a lifting assembly of the high-area net rack unit, and then hovering; low-area net rack units are assembled, low-area net rack lifting assemblies are arranged and installed, and lifting ropes are in a stretched straight state; a gear filling rod piece between the high-area net rack unit and the low-area net rack unit is installed in an inlaying mode; the high-area net rack temporary lifting assembly is dismantled; and the high-area net rack lifting assembly and the low-area net rack lifting assembly are used for synchronously lifting the high-area net rack unit and the low-area net rack unit to the designed elevation. According to the step-shaped net rack relay lifting lifting point conversion method, relay conversion lifting is achieved, it is avoided that an ultrahigh lifting support is arranged on the top of the steel column, it is guaranteed that the construction process is safe and reliable, and the application prospect is good.
本发明公开了一种台阶状网架接力提升吊点转换的方法,步骤:拼装高区网架单元,设置并安高区网架提升组件和高区网架临时提升组件;利用高区网架单元的吊装组件将高区网架单元提升至与低区网架单元要求的设计拼装高度后悬停;拼装低区网架单元,设置并安装低区网架提升组件且使得吊装绳处于绷直状态;嵌补安装高区网架单元与低区网架单元之间的补档杆件;拆除高区网架临时提升组件;利用高区网架提升组件和低区网架提升组件同步提升高区网架单元和低区网架单元直到设计标高。本发明的台阶状网架接力提升吊点转换的方法,接力转换提升,避免了在钢柱顶设置超高的提升支架,保证了施工过程安全可靠,应用前景好。
Step-shaped net rack relay lifting suspension point conversion method
The invention discloses a step-shaped net rack relay lifting suspension point conversion method, which comprises the following steps of: assembling high-area net rack units, and arranging and installing a high-area net rack lifting assembly and a high-area net rack temporary lifting assembly; lifting the high-area net rack unit to a designed assembly height required by the low-area net rack unit by using a lifting assembly of the high-area net rack unit, and then hovering; low-area net rack units are assembled, low-area net rack lifting assemblies are arranged and installed, and lifting ropes are in a stretched straight state; a gear filling rod piece between the high-area net rack unit and the low-area net rack unit is installed in an inlaying mode; the high-area net rack temporary lifting assembly is dismantled; and the high-area net rack lifting assembly and the low-area net rack lifting assembly are used for synchronously lifting the high-area net rack unit and the low-area net rack unit to the designed elevation. According to the step-shaped net rack relay lifting lifting point conversion method, relay conversion lifting is achieved, it is avoided that an ultrahigh lifting support is arranged on the top of the steel column, it is guaranteed that the construction process is safe and reliable, and the application prospect is good.
本发明公开了一种台阶状网架接力提升吊点转换的方法,步骤:拼装高区网架单元,设置并安高区网架提升组件和高区网架临时提升组件;利用高区网架单元的吊装组件将高区网架单元提升至与低区网架单元要求的设计拼装高度后悬停;拼装低区网架单元,设置并安装低区网架提升组件且使得吊装绳处于绷直状态;嵌补安装高区网架单元与低区网架单元之间的补档杆件;拆除高区网架临时提升组件;利用高区网架提升组件和低区网架提升组件同步提升高区网架单元和低区网架单元直到设计标高。本发明的台阶状网架接力提升吊点转换的方法,接力转换提升,避免了在钢柱顶设置超高的提升支架,保证了施工过程安全可靠,应用前景好。
Step-shaped net rack relay lifting suspension point conversion method
一种台阶状网架接力提升吊点转换的方法
CHEN HUI (Autor:in) / SHENG YISHAN (Autor:in) / CHEN PENGXU (Autor:in) / FAN DENGCHAO (Autor:in) / GAO YONGQIANG (Autor:in)
12.09.2023
Patent
Elektronische Ressource
Chinesisch
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2020
|Europäisches Patentamt | 2023
|