Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Construction method suitable for steel structure corridor
The invention belongs to the technical field of building engineering, and provides a construction method suitable for a steel structure corridor, by dividing a forming area of the steel structure corridor and dividing forming sections of the steel structure corridor based on the divided area, segmented and partitioned manufacturing of the steel structure corridor can be achieved, and the construction efficiency of the steel structure corridor is improved. The working efficiency can be better improved; and then through the arrangement of a first-stage lifting device and a second-stage lifting device, lifting of the assembly section located in the ground area, butt joint between the assembly section located in the building skirt area and butt joint between the assembly section located in the building skirt area and the first pre-assembly section and the second pre-assembly section can be achieved, and then construction of the foundation framework of the steel structure corridor is completed. In the whole process, a partitioned design and segmented lifting mode is adopted, the method can be applied to construction of the steel structure corridor of the super-large-span super-high-rise building, the safety, efficiency, cost, construction period and other factors in the whole manufacturing process can be better controlled, and better economic benefits are achieved.
本申请属于建筑工程技术领域,提供有一种适用于钢结构连廊的施工方法,通过对钢结构连廊的成型区域进行划分,同时基于划分的区域进行钢结构连廊的成型段落划分,从而可以实现钢结构连廊的分段及分区式制作,工作效率可以得到更好的提高;然后通过设置的一级起吊装置、二级起吊装置,可以用于实现位于地面区域的拼装段的提升、与楼裙区域上的拼装段之间的对接以及与第一预装段、第二预装段之间的对接,进而完成钢结构连廊的基础架构的施工。整个过程中采用分区设计以及分段提升的形式,可以应用于超大跨度超高层的钢结构连廊的施工中,并且整个制作过程中的安全、效率、成本及工期等因素都可以得到更好的把控,具有更好的经济效益。
Construction method suitable for steel structure corridor
The invention belongs to the technical field of building engineering, and provides a construction method suitable for a steel structure corridor, by dividing a forming area of the steel structure corridor and dividing forming sections of the steel structure corridor based on the divided area, segmented and partitioned manufacturing of the steel structure corridor can be achieved, and the construction efficiency of the steel structure corridor is improved. The working efficiency can be better improved; and then through the arrangement of a first-stage lifting device and a second-stage lifting device, lifting of the assembly section located in the ground area, butt joint between the assembly section located in the building skirt area and butt joint between the assembly section located in the building skirt area and the first pre-assembly section and the second pre-assembly section can be achieved, and then construction of the foundation framework of the steel structure corridor is completed. In the whole process, a partitioned design and segmented lifting mode is adopted, the method can be applied to construction of the steel structure corridor of the super-large-span super-high-rise building, the safety, efficiency, cost, construction period and other factors in the whole manufacturing process can be better controlled, and better economic benefits are achieved.
本申请属于建筑工程技术领域,提供有一种适用于钢结构连廊的施工方法,通过对钢结构连廊的成型区域进行划分,同时基于划分的区域进行钢结构连廊的成型段落划分,从而可以实现钢结构连廊的分段及分区式制作,工作效率可以得到更好的提高;然后通过设置的一级起吊装置、二级起吊装置,可以用于实现位于地面区域的拼装段的提升、与楼裙区域上的拼装段之间的对接以及与第一预装段、第二预装段之间的对接,进而完成钢结构连廊的基础架构的施工。整个过程中采用分区设计以及分段提升的形式,可以应用于超大跨度超高层的钢结构连廊的施工中,并且整个制作过程中的安全、效率、成本及工期等因素都可以得到更好的把控,具有更好的经济效益。
Construction method suitable for steel structure corridor
一种适用于钢结构连廊的施工方法
LIU XIAOHONG (Autor:in) / WU CHENGYUN (Autor:in) / CHENG JIAN (Autor:in) / WANG ZHE (Autor:in) / XU XIAOLONG (Autor:in) / LIN JINJUN (Autor:in) / ZHANG ZEYU (Autor:in) / WANG XINYUAN (Autor:in) / SU JINHONG (Autor:in)
20.10.2023
Patent
Elektronische Ressource
Chinesisch
Large-span steel structure corridor construction method
Europäisches Patentamt | 2024
|Overhead suspended ceiling construction method suitable for super high-rise steel corridor
Europäisches Patentamt | 2023
|Steel structure corridor structure and hoisting construction method
Europäisches Patentamt | 2020
|Steel structure corridor support and construction method thereof
Europäisches Patentamt | 2024
|