Emergency and permanent reinforcement system construction method for water-rich accumulation body landslide treatment
The invention belongs to the technical field of slope treatment, discloses an emergency and permanent reinforcement system construction method for water-rich accumulation body landslide treatment, and aims to solve the problem of long construction period caused by adopting slide-resistant piles to treat slopes. The mountainous area water-rich landslide can be quickly treated (namely, the first row of steel pipe piles, the second row of steel pipe piles and the anchor rods are utilized to form a temporary supporting system), so that mountainous area road traffic can be quickly recovered, and the influence of the landslide on mountainous area traffic roads is reduced. Meanwhile, the system can be used as a permanent reinforcing system (the first process steel pipe piles, the second process steel pipe piles and the anchor rods are jointly formed), the stability of the mountainous area water-rich slope structure is ensured, the follow-up landslide risk is reduced, and the safety of mountainous area road traffic is improved.
本发明属于边坡治理技术领域,公开了用于富水堆积体滑坡治理的应急及永久加固体系施工方法,为了解决采用抗滑桩来治理边坡导致施工周期长的问题。本发明能够快速的对山区富水滑坡进行处理(即利用第一排钢管桩、第二排钢管桩和锚杆形成临时支撑体系),以便于快速的恢复山区道路交通,降低滑坡对山区交通道路的影响。同时本发明既能够作为,同时又能够用作永久加固体系(第一工序钢管桩和第二工序钢管桩以及锚杆共同形成),确保山区富水边坡结构的稳定性,降低后续滑坡风险,提高山区道路交通的安全性。
Emergency and permanent reinforcement system construction method for water-rich accumulation body landslide treatment
The invention belongs to the technical field of slope treatment, discloses an emergency and permanent reinforcement system construction method for water-rich accumulation body landslide treatment, and aims to solve the problem of long construction period caused by adopting slide-resistant piles to treat slopes. The mountainous area water-rich landslide can be quickly treated (namely, the first row of steel pipe piles, the second row of steel pipe piles and the anchor rods are utilized to form a temporary supporting system), so that mountainous area road traffic can be quickly recovered, and the influence of the landslide on mountainous area traffic roads is reduced. Meanwhile, the system can be used as a permanent reinforcing system (the first process steel pipe piles, the second process steel pipe piles and the anchor rods are jointly formed), the stability of the mountainous area water-rich slope structure is ensured, the follow-up landslide risk is reduced, and the safety of mountainous area road traffic is improved.
本发明属于边坡治理技术领域,公开了用于富水堆积体滑坡治理的应急及永久加固体系施工方法,为了解决采用抗滑桩来治理边坡导致施工周期长的问题。本发明能够快速的对山区富水滑坡进行处理(即利用第一排钢管桩、第二排钢管桩和锚杆形成临时支撑体系),以便于快速的恢复山区道路交通,降低滑坡对山区交通道路的影响。同时本发明既能够作为,同时又能够用作永久加固体系(第一工序钢管桩和第二工序钢管桩以及锚杆共同形成),确保山区富水边坡结构的稳定性,降低后续滑坡风险,提高山区道路交通的安全性。
Emergency and permanent reinforcement system construction method for water-rich accumulation body landslide treatment
用于富水堆积体滑坡治理的应急及永久加固体系施工方法
21.11.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Structure inducing accumulation body landslide and construction method thereof
Europäisches Patentamt | 2021
|Europäisches Patentamt | 2023
|Construction method for emergency rescue treatment of soil landslide through high polymer grouting
Europäisches Patentamt | 2021
|Landslide caused by accumulation of water
Engineering Index Backfile | 1885