Fabricated construction method for water cooling machine room of subway station
The invention relates to the field of underground building construction, in particular to a subway station water cooling machine room assembly type construction method which comprises the steps that all equipment modules are prefabricated in a factory; placing the equipment modules in a factory in a manner of simulating actual mounting positions in the cold water machine room, connecting the equipment modules by using pipelines, and performing trial operation; all the equipment modules passing the pilot run are hoisted underground, and the equipment modules are moved to the corresponding installation foundations in the water cooling machine room through moving equipment; connecting all the equipment modules which are moved in place by using pipelines and carrying out trial operation; the installation bases of all the equipment modules are connected with the corresponding installation foundations through trial operation, so that the overall assembly construction progress of the water cooling machine room is not prone to being affected.
本申请涉及地下建筑施工的领域,尤其是涉及一种地铁车站冷水机房装配式施工方法,包括在工厂中进行各设备模块的预制;将各设备模块在工厂内模拟冷水机房内实际安装位置进行放置并使用管线进行连接并试运行;试运行通过的各设备模块吊入至地下,并使用移动设备将设备模块移动至冷水机房内对应安装基础上;对移动到位的各设备模块使用管线连接并进行试运行;试运行通过的各设备模块的安装底座和对应的安装基础进行连接,使得冷水机房整体装配施工进度不易受到影响。
Fabricated construction method for water cooling machine room of subway station
The invention relates to the field of underground building construction, in particular to a subway station water cooling machine room assembly type construction method which comprises the steps that all equipment modules are prefabricated in a factory; placing the equipment modules in a factory in a manner of simulating actual mounting positions in the cold water machine room, connecting the equipment modules by using pipelines, and performing trial operation; all the equipment modules passing the pilot run are hoisted underground, and the equipment modules are moved to the corresponding installation foundations in the water cooling machine room through moving equipment; connecting all the equipment modules which are moved in place by using pipelines and carrying out trial operation; the installation bases of all the equipment modules are connected with the corresponding installation foundations through trial operation, so that the overall assembly construction progress of the water cooling machine room is not prone to being affected.
本申请涉及地下建筑施工的领域,尤其是涉及一种地铁车站冷水机房装配式施工方法,包括在工厂中进行各设备模块的预制;将各设备模块在工厂内模拟冷水机房内实际安装位置进行放置并使用管线进行连接并试运行;试运行通过的各设备模块吊入至地下,并使用移动设备将设备模块移动至冷水机房内对应安装基础上;对移动到位的各设备模块使用管线连接并进行试运行;试运行通过的各设备模块的安装底座和对应的安装基础进行连接,使得冷水机房整体装配施工进度不易受到影响。
Fabricated construction method for water cooling machine room of subway station
一种地铁车站冷水机房装配式施工方法
CHEN JUN (Autor:in) / ZHANG GANGLI (Autor:in) / YAN HUALI (Autor:in) / HUANG TINGTING (Autor:in) / WANG QICHAO (Autor:in) / DU SHAOTENG (Autor:in) / WU FAN (Autor:in)
28.11.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
B66F
HOISTING, LIFTING, HAULING, OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
,
Hub-, Verhol- oder Schubvorrichtungen, soweit nicht anderweitig vorgesehen, z.B. Vorrichtungen mit unmittelbarer Krafteinwirkung auf die Last
/
B25H
Werkstatteinrichtungen, z.B. zum Anreißen von Werkstücken
,
WORKSHOP EQUIPMENT, e.g. FOR MARKING-OUT WORK
/
E04H
Gebäude oder ähnliche Bauwerke für besondere Zwecke
,
BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES
/
F16H
Getriebe
,
GEARING
Construction method of fabricated subway station and fabricated subway station
Europäisches Patentamt | 2024
|Subway station water cooling machine room assembly type construction method based on BIM
Europäisches Patentamt | 2021
|Fabricated subway station waterproof system construction method
Europäisches Patentamt | 2024
|