Broken surge communication construction method
The construction method comprises the following steps that the topographic conditions between every two adjacent head-breaking surges are obtained, and the topographic conditions comprise a section with open channel excavation conditions, a section with a road function and a dike; different construction modes are selected according to different topographic conditions, and when the topographic condition is a section with the open channel excavation preparation condition, the construction mode is sheet pile vertical type section construction; when the terrain condition is a section bearing the road function, the construction mode is shallow-buried box culvert construction; when the terrain condition is a dike, the construction mode is upstream face slope construction; construction is carried out based on the selected construction mode so as to communicate the two adjacent broken surges; and the head-broken surge at the head end is communicated with the outer river channel, so that flowing water circulation is realized. According to the method, the problem that the existing broken end surge is difficult to effectively treat through a conventional biological method is solved, and then the black and odorous condition caused by siltation of sludge and accumulation of microorganisms is avoided.
本发明公开了一种断头涌连通的施工方法,包括如下步骤:获取相邻的两条断头涌之间的地形情况,地形情况包括:具备明渠开挖条件的地段、承担道路功能的地段以及堤防;根据不同的地形情况选择不同的施工方式,当地形情况为备明渠开挖条件的地段时,施工方式为进行板桩直立式断面施工;当地形情况为承担道路功能的地段时,施工方式为进行浅埋箱涵施工;当地形情况为堤防时,施工方式为进行迎水面坡施工;基于选择的施工方式进行施工,以连通相邻的两条断头涌;将位于首端的断头涌与外河道连通,实现活水流通。本发明解决了现有的断头涌通过常规的生物方法难以进行有效治理的问题,进而避免了淤泥的淤积以及微生物的积累导致的黑臭情况出现。
Broken surge communication construction method
The construction method comprises the following steps that the topographic conditions between every two adjacent head-breaking surges are obtained, and the topographic conditions comprise a section with open channel excavation conditions, a section with a road function and a dike; different construction modes are selected according to different topographic conditions, and when the topographic condition is a section with the open channel excavation preparation condition, the construction mode is sheet pile vertical type section construction; when the terrain condition is a section bearing the road function, the construction mode is shallow-buried box culvert construction; when the terrain condition is a dike, the construction mode is upstream face slope construction; construction is carried out based on the selected construction mode so as to communicate the two adjacent broken surges; and the head-broken surge at the head end is communicated with the outer river channel, so that flowing water circulation is realized. According to the method, the problem that the existing broken end surge is difficult to effectively treat through a conventional biological method is solved, and then the black and odorous condition caused by siltation of sludge and accumulation of microorganisms is avoided.
本发明公开了一种断头涌连通的施工方法,包括如下步骤:获取相邻的两条断头涌之间的地形情况,地形情况包括:具备明渠开挖条件的地段、承担道路功能的地段以及堤防;根据不同的地形情况选择不同的施工方式,当地形情况为备明渠开挖条件的地段时,施工方式为进行板桩直立式断面施工;当地形情况为承担道路功能的地段时,施工方式为进行浅埋箱涵施工;当地形情况为堤防时,施工方式为进行迎水面坡施工;基于选择的施工方式进行施工,以连通相邻的两条断头涌;将位于首端的断头涌与外河道连通,实现活水流通。本发明解决了现有的断头涌通过常规的生物方法难以进行有效治理的问题,进而避免了淤泥的淤积以及微生物的积累导致的黑臭情况出现。
Broken surge communication construction method
一种断头涌连通的施工方法
CHEN ZHENGBING (Autor:in) / ZU CHAOFENG (Autor:in) / TANG JIAYUAN (Autor:in) / FAN RONG (Autor:in) / LOU XIAOKANG (Autor:in) / CAO GANG (Autor:in) / LIU JIQIANG (Autor:in)
16.04.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02B
HYDRAULIC ENGINEERING
,
Wasserbau
/
E01F
ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
,
Zusätzliche Baumaßnahmen, wie die Ausstattung von Straßen oder die bauliche Ausbildung von Bahnsteigen, Landeplätzen für Hubschrauber, Wegweisern, Schneezäunen oder dgl.
/
E02D
FOUNDATIONS
,
Gründungen
Broken-end surge scouring and silting structure and scouring and silting method
Europäisches Patentamt | 2021
|Construction Report: Construction methodology of surge shaft
Online Contents | 2003
|Broken pile underpinning and jacking construction method
Europäisches Patentamt | 2024
|Pile-in-pile broken pile splicing construction method
Europäisches Patentamt | 2020
|Construction method of heat insulation broken bridge window
Europäisches Patentamt | 2023
|