Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Pretreatment method for high-pressure jet grouting pile construction without slurry return
The invention discloses a pretreatment method without slurry return in high-pressure jet grouting pile construction, which is characterized in that a slurry jacking process is set in a drilling construction stage before slurry spraying construction, a slurry jacking material is replaced by preset adjusting slurry, treatment can be completed by using a drilling machine for pre-drilling of a high-pressure jet grouting pile, and slurry jacking construction is completed while pre-drilling of the high-pressure jet grouting pile is performed. Compared with the prior art, the method has the advantages that long-time static spraying of the high-pressure jet grouting pile is avoided when the high-pressure jet grouting pile does not return during grout spraying, construction time is effectively saved, construction efficiency is improved by more than 30%, materials for preparing the slurry are convenient to obtain, cost is low, a treatment mode of adding water glass in the prior art is not needed, and pollution to the environment is greatly reduced.
本发明公开了一种高压旋喷桩施工不返浆的预处理方法,在喷浆施工前钻孔施工阶段同时设置了压浆工序,将压浆材料换成预先设置的调节泥浆,利用高压旋喷桩预钻孔的钻机即可完成处理,且在高压旋喷桩预钻孔的同时完成压浆施工,避免了高压旋喷桩遇喷浆不返浆时长时间静喷的情况,有效的节省了施工时间,提高了施工效率,提高施工效率30%以上,且调制泥浆取材方便,成本低,无需如现有技术所采用加入水玻璃的处理方式,大大减少了对环境的污染。
Pretreatment method for high-pressure jet grouting pile construction without slurry return
The invention discloses a pretreatment method without slurry return in high-pressure jet grouting pile construction, which is characterized in that a slurry jacking process is set in a drilling construction stage before slurry spraying construction, a slurry jacking material is replaced by preset adjusting slurry, treatment can be completed by using a drilling machine for pre-drilling of a high-pressure jet grouting pile, and slurry jacking construction is completed while pre-drilling of the high-pressure jet grouting pile is performed. Compared with the prior art, the method has the advantages that long-time static spraying of the high-pressure jet grouting pile is avoided when the high-pressure jet grouting pile does not return during grout spraying, construction time is effectively saved, construction efficiency is improved by more than 30%, materials for preparing the slurry are convenient to obtain, cost is low, a treatment mode of adding water glass in the prior art is not needed, and pollution to the environment is greatly reduced.
本发明公开了一种高压旋喷桩施工不返浆的预处理方法,在喷浆施工前钻孔施工阶段同时设置了压浆工序,将压浆材料换成预先设置的调节泥浆,利用高压旋喷桩预钻孔的钻机即可完成处理,且在高压旋喷桩预钻孔的同时完成压浆施工,避免了高压旋喷桩遇喷浆不返浆时长时间静喷的情况,有效的节省了施工时间,提高了施工效率,提高施工效率30%以上,且调制泥浆取材方便,成本低,无需如现有技术所采用加入水玻璃的处理方式,大大减少了对环境的污染。
Pretreatment method for high-pressure jet grouting pile construction without slurry return
一种高压旋喷桩施工不返浆的预处理方法
SEO MOON-KIL (Autor:in) / ZHANG JUNMING (Autor:in) / ZHOU QINAN (Autor:in) / HE GANG (Autor:in) / ZHU BIN (Autor:in) / LU JIANPEI (Autor:in) / YANG WEI (Autor:in) / LU BIAO (Autor:in) / KONG LEI (Autor:in) / WANG YUTING (Autor:in)
19.04.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Europäisches Patentamt | 2024
|Construction method for high-pressure jet grouting based on slurry return conductivity data
Europäisches Patentamt | 2022
|Slurry return prevention device and method for grouting at pile end of tubular pile
Europäisches Patentamt | 2023
|