Continuous beam swivel dismantling method
The invention discloses a continuous beam swivel dismantling method, which belongs to the technical field of bridge construction, and comprises the following steps: erecting a spherical hinge slideway bracket and a side span bracket, constructing a 0 # block bracket, and mounting a spherical hinge on the pier top; the cranes are installed on the two sides of the mid-span closure section, and the mid-span closure section is transversely cut and lowered to the ground; the side span cast-in-place section and the side span closure section are cut and removed to form a T-shaped structure, and the cut side span cast-in-place section and the cut side span closure section are lowered to the ground; the 0 # block permanent support is dismantled, and the spherical hinge is stressed; the two sides of the T-shaped structure are weighed and counterweighted; a rotation jack is installed to push the T-shaped structure to rotate; a pier beam temporary consolidation structure is installed, and locking of the 0 # block is completed; the T-shaped structure section is segmented and cut from the two ends to the middle, and is lowered to the ground to be dismantled and carried away; and the 0 # blocks are segmented and dismantled one by one, and dismantling of the cross-road bridge structure is completed.
本发明公开了一种连续梁转体拆除方法,属于桥梁施工技术领域,包括:搭设球铰滑道支架和边跨支架,0#块支架施工,并在墩顶安装球铰;中跨合龙段两侧安装吊机,横向切割中跨合龙段并下放至地面;切割拆除边跨现浇段和边跨合龙段形成‘T’构,并将切割下来的边跨现浇段和边跨合龙段下放至地面;拆除0#块永久支座,使球铰受力;‘T’构两侧进行称重并配重;安装转体千斤顶推动‘T’构进行转体;在安装墩梁临时固结结构,完成0#块的锁定;‘T’构段由两端向中间进行分段切割,并下放至地面拆除运走;逐块分割拆除0#块,完成跨道路桥梁结构的拆除。
Continuous beam swivel dismantling method
The invention discloses a continuous beam swivel dismantling method, which belongs to the technical field of bridge construction, and comprises the following steps: erecting a spherical hinge slideway bracket and a side span bracket, constructing a 0 # block bracket, and mounting a spherical hinge on the pier top; the cranes are installed on the two sides of the mid-span closure section, and the mid-span closure section is transversely cut and lowered to the ground; the side span cast-in-place section and the side span closure section are cut and removed to form a T-shaped structure, and the cut side span cast-in-place section and the cut side span closure section are lowered to the ground; the 0 # block permanent support is dismantled, and the spherical hinge is stressed; the two sides of the T-shaped structure are weighed and counterweighted; a rotation jack is installed to push the T-shaped structure to rotate; a pier beam temporary consolidation structure is installed, and locking of the 0 # block is completed; the T-shaped structure section is segmented and cut from the two ends to the middle, and is lowered to the ground to be dismantled and carried away; and the 0 # blocks are segmented and dismantled one by one, and dismantling of the cross-road bridge structure is completed.
本发明公开了一种连续梁转体拆除方法,属于桥梁施工技术领域,包括:搭设球铰滑道支架和边跨支架,0#块支架施工,并在墩顶安装球铰;中跨合龙段两侧安装吊机,横向切割中跨合龙段并下放至地面;切割拆除边跨现浇段和边跨合龙段形成‘T’构,并将切割下来的边跨现浇段和边跨合龙段下放至地面;拆除0#块永久支座,使球铰受力;‘T’构两侧进行称重并配重;安装转体千斤顶推动‘T’构进行转体;在安装墩梁临时固结结构,完成0#块的锁定;‘T’构段由两端向中间进行分段切割,并下放至地面拆除运走;逐块分割拆除0#块,完成跨道路桥梁结构的拆除。
Continuous beam swivel dismantling method
一种连续梁转体拆除方法
LI CHAO (Autor:in) / LIU JIANXUN (Autor:in) / PAN LONG (Autor:in) / JIANG FENGQING (Autor:in) / ZHANG CHANGXUAN (Autor:in) / YANG CHAO (Autor:in) / JIANG LANG (Autor:in) / ZHANG JINWANG (Autor:in) / WANG GUANGSONG (Autor:in) / GUO ZHIQI (Autor:in)
30.04.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Swivel dismantling device and method for cross-railway continuous rigid frame bridge
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2024
|Dismantling method of double-layer swivel bridge construction supporting bracket
Europäisches Patentamt | 2023
|Prestressed concrete continuous beam dismantling method
Europäisches Patentamt | 2021
|