Artificial island construction method for synchronously constructing filling and underground fabricated structure
The invention discloses an artificial island building method for synchronously building a filling structure and an underground fabricated structure. The method comprises the steps that cofferdams are oppositely built on the outer side of a preset area; dividing the preset area into a plurality of construction areas and filling soil to form a foundation; the foundation is treated to form a construction working face, construction is conducted on the area, corresponding to the fabricated structure, of the construction working face, and foundation pit excavation is conducted on the area corresponding to the high-rise building; and the fabricated structures are installed layer by layer, and a foundation pit of the high-rise building is filled according to the floor height of the single-layer fabricated structure. The cofferdams are oppositely built at the two ends of the outer side of the preset area, soil filling is synchronously conducted on the construction area corresponding to the cofferdams in the process, after the cofferdams are enclosed, a foundation is formed in the construction area, treatment can be conducted according to the construction requirements of an assembly type structure and a high-rise building through treatment, filling is matched while layer-by-layer construction is conducted, and the construction efficiency is improved. The effect of synchronous construction of underground and overground structures is achieved, the construction steps can be reduced, the engineering amount and the engineering period are shortened, and the construction efficiency is improved.
本发明公开了一种填筑和地下装配式结构同步建造的人工海岛修建方法,该方法包括:在预定区域的外侧相向建造围堰;将预定区域划分为若干个施工区域并填土形成地基;处理地基形成施工工作面,对施工工作面上对应装配式结构的区域施工,对应高层建筑的区域进行基坑挖掘;逐层安装将装配式结构,并根据单层装配式结构的层高对高层建筑的基坑进行填筑。本发明在预定区域的外侧两端相向建造围堰,过程中同步对围堰对应的施工区域填土,在围堰围合后,施工区域形成地基,经处理可根据装配式结构和高层建筑的建造需求进行处理,在逐层建造的同时配合填筑,形成地下与地上结构同步施工的效果,可减少施工步骤,缩减工程量和工程周期,提高施工效率。
Artificial island construction method for synchronously constructing filling and underground fabricated structure
The invention discloses an artificial island building method for synchronously building a filling structure and an underground fabricated structure. The method comprises the steps that cofferdams are oppositely built on the outer side of a preset area; dividing the preset area into a plurality of construction areas and filling soil to form a foundation; the foundation is treated to form a construction working face, construction is conducted on the area, corresponding to the fabricated structure, of the construction working face, and foundation pit excavation is conducted on the area corresponding to the high-rise building; and the fabricated structures are installed layer by layer, and a foundation pit of the high-rise building is filled according to the floor height of the single-layer fabricated structure. The cofferdams are oppositely built at the two ends of the outer side of the preset area, soil filling is synchronously conducted on the construction area corresponding to the cofferdams in the process, after the cofferdams are enclosed, a foundation is formed in the construction area, treatment can be conducted according to the construction requirements of an assembly type structure and a high-rise building through treatment, filling is matched while layer-by-layer construction is conducted, and the construction efficiency is improved. The effect of synchronous construction of underground and overground structures is achieved, the construction steps can be reduced, the engineering amount and the engineering period are shortened, and the construction efficiency is improved.
本发明公开了一种填筑和地下装配式结构同步建造的人工海岛修建方法,该方法包括:在预定区域的外侧相向建造围堰;将预定区域划分为若干个施工区域并填土形成地基;处理地基形成施工工作面,对施工工作面上对应装配式结构的区域施工,对应高层建筑的区域进行基坑挖掘;逐层安装将装配式结构,并根据单层装配式结构的层高对高层建筑的基坑进行填筑。本发明在预定区域的外侧两端相向建造围堰,过程中同步对围堰对应的施工区域填土,在围堰围合后,施工区域形成地基,经处理可根据装配式结构和高层建筑的建造需求进行处理,在逐层建造的同时配合填筑,形成地下与地上结构同步施工的效果,可减少施工步骤,缩减工程量和工程周期,提高施工效率。
Artificial island construction method for synchronously constructing filling and underground fabricated structure
一种填筑和地下装配式结构同步建造的人工海岛修建方法
CHEN XIANGSHENG (Autor:in) / SU DONG (Autor:in) / LI QIANG (Autor:in) / ZHOU JINWEI (Autor:in) / SUN XIAOHUI (Autor:in) / FU YANBIN (Autor:in) / LAI YANI (Autor:in) / ZHOU YUEFU (Autor:in) / ZHANG MING (Autor:in) / CHEN CHANGQING (Autor:in)
31.05.2024
Patent
Elektronische Ressource
Chinesisch
Method for synchronously constructing high part and low part of stepped underground structure
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2021
|Method for removing underground air-raid shelter and synchronously constructing foundation pit
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2023
|Artificial filling island airport runway structure and construction method thereof
Europäisches Patentamt | 2020
|