Construction method for sludge stockpiling in waste slag field in barrage foundation pit excavation
The invention discloses a construction method for sludge stockpiling in a waste slag field in barrage foundation pit excavation, the waste slag field is divided into a plurality of waste slag areas, lofting and grouping are carried out, and each waste slag area group comprises three waste slag areas; each residue discarding area group comprises three residue discarding areas which are used for sequentially carrying out the operation procedures of residue discarding, bulldozing and airing, the operation procedures implemented by the adjacent residue discarding areas are different, and the steps are cycled to form stepped line production. Limited time and space are fully utilized, the contradiction of sludge stacking and abandoning operation in time and space is solved, the sludge stacking and abandoning amount is increased, the time of sludge transportation and stacking and abandoning operation is shortened, and the construction efficiency of sludge foundation pit excavation is greatly improved.
本发明公开了拦河坝基坑开挖中弃渣场淤泥堆存的施工方法,将弃渣场场地划分为多个弃渣区并进行放样和分组,所述每个弃渣区组包括三个弃渣区;每个弃渣区组包括三个弃渣区依次进行弃渣、推平、晾晒的作业工序,相邻弃渣区实施的作业工序不相同,如此循环形成台阶式流水作业。充分利用有限的时间和空间,解决淤泥堆弃作业时空上的矛盾,增加淤泥的堆弃量,缩短淤泥运输和堆弃作业的时间,大幅提高淤泥基坑开挖的施工效率。
Construction method for sludge stockpiling in waste slag field in barrage foundation pit excavation
The invention discloses a construction method for sludge stockpiling in a waste slag field in barrage foundation pit excavation, the waste slag field is divided into a plurality of waste slag areas, lofting and grouping are carried out, and each waste slag area group comprises three waste slag areas; each residue discarding area group comprises three residue discarding areas which are used for sequentially carrying out the operation procedures of residue discarding, bulldozing and airing, the operation procedures implemented by the adjacent residue discarding areas are different, and the steps are cycled to form stepped line production. Limited time and space are fully utilized, the contradiction of sludge stacking and abandoning operation in time and space is solved, the sludge stacking and abandoning amount is increased, the time of sludge transportation and stacking and abandoning operation is shortened, and the construction efficiency of sludge foundation pit excavation is greatly improved.
本发明公开了拦河坝基坑开挖中弃渣场淤泥堆存的施工方法,将弃渣场场地划分为多个弃渣区并进行放样和分组,所述每个弃渣区组包括三个弃渣区;每个弃渣区组包括三个弃渣区依次进行弃渣、推平、晾晒的作业工序,相邻弃渣区实施的作业工序不相同,如此循环形成台阶式流水作业。充分利用有限的时间和空间,解决淤泥堆弃作业时空上的矛盾,增加淤泥的堆弃量,缩短淤泥运输和堆弃作业的时间,大幅提高淤泥基坑开挖的施工效率。
Construction method for sludge stockpiling in waste slag field in barrage foundation pit excavation
一种拦河坝基坑开挖中弃渣场淤泥堆存的施工方法
YANG CHUAN (Autor:in) / LI HONGLIN (Autor:in) / LAN TIAN (Autor:in) / MI GANGLI (Autor:in) / LI JIAWEI (Autor:in)
02.07.2024
Patent
Elektronische Ressource
Chinesisch
Steel slag stockpiling site covering structure and application method
Europäisches Patentamt | 2022
|Method for stockpiling and pretreating hot-stewed steel slag
Europäisches Patentamt | 2022
|Canal excavation on the Sukkur barrage project
Engineering Index Backfile | 1929