Steel trestle and construction method thereof
The invention relates to the field of bridge construction, in particular to a steel trestle and a construction method thereof.The steel trestle comprises a pile foundation and a plurality of bailey beams, the multiple bailey beams form a framework, a fixing rod is fixed to one end of the framework in the length direction, a fixing cavity allowing the fixing rod to be embedded is formed in the other end of the framework in the length direction, and a reinforcing assembly is connected to the framework; the reinforcing assembly comprises a reinforcing rod and a reinforcing elastic piece, a reinforcing cavity for the reinforcing rod to slide is formed in the inner wall of the fixing cavity, one end of the reinforcing elastic piece in the elastic direction is connected to the inner wall of the reinforcing cavity, and the other end of the reinforcing elastic piece in the elastic direction is connected to the surface of the reinforcing rod. The reinforcing rods and the reinforcing elastic pieces are arranged, the outer walls of the reinforcing rods abut against the inner walls of the reinforcing grooves to form fixation, the fixing rods are not prone to being separated from the fixing cavities, automatic connection of the adjacent frameworks is achieved, workers do not need to connect the frameworks through screws or other connecting pieces, the construction steps of the frameworks are reduced, the construction period of the steel trestle is shortened, and the construction efficiency of the steel trestle is improved. Therefore, the construction efficiency of the steel trestle is improved.
本申请涉及桥梁施工的领域,尤其是一种钢栈桥及其建造方法,包括桩基和多个贝雷梁,多个贝雷梁组成骨架,骨架长度方向的一端固定有固定杆,骨架长度方向的另一端开始有供固定杆嵌入的固定腔,骨架上连接有加固组件,加固组件包括加固杆和加固弹性件,固定腔内壁开设有供加固杆滑移的加固腔,加固弹性件弹力方向的一端连接在加固腔内壁上,加固弹性件弹力方向的另一端连接在加固杆表面。本申请中加固杆和加固弹性件的设置,加固杆外壁抵紧加固槽内壁形成固定,使固定杆不易脱离固定腔,实现相邻骨架的自动化连接,无需工作人员通过螺钉或者其它连接件对骨架进行连接,减少骨架的施工步骤,缩短对钢栈桥的施工周期,从而提高对钢栈桥的施工效率。
Steel trestle and construction method thereof
The invention relates to the field of bridge construction, in particular to a steel trestle and a construction method thereof.The steel trestle comprises a pile foundation and a plurality of bailey beams, the multiple bailey beams form a framework, a fixing rod is fixed to one end of the framework in the length direction, a fixing cavity allowing the fixing rod to be embedded is formed in the other end of the framework in the length direction, and a reinforcing assembly is connected to the framework; the reinforcing assembly comprises a reinforcing rod and a reinforcing elastic piece, a reinforcing cavity for the reinforcing rod to slide is formed in the inner wall of the fixing cavity, one end of the reinforcing elastic piece in the elastic direction is connected to the inner wall of the reinforcing cavity, and the other end of the reinforcing elastic piece in the elastic direction is connected to the surface of the reinforcing rod. The reinforcing rods and the reinforcing elastic pieces are arranged, the outer walls of the reinforcing rods abut against the inner walls of the reinforcing grooves to form fixation, the fixing rods are not prone to being separated from the fixing cavities, automatic connection of the adjacent frameworks is achieved, workers do not need to connect the frameworks through screws or other connecting pieces, the construction steps of the frameworks are reduced, the construction period of the steel trestle is shortened, and the construction efficiency of the steel trestle is improved. Therefore, the construction efficiency of the steel trestle is improved.
本申请涉及桥梁施工的领域,尤其是一种钢栈桥及其建造方法,包括桩基和多个贝雷梁,多个贝雷梁组成骨架,骨架长度方向的一端固定有固定杆,骨架长度方向的另一端开始有供固定杆嵌入的固定腔,骨架上连接有加固组件,加固组件包括加固杆和加固弹性件,固定腔内壁开设有供加固杆滑移的加固腔,加固弹性件弹力方向的一端连接在加固腔内壁上,加固弹性件弹力方向的另一端连接在加固杆表面。本申请中加固杆和加固弹性件的设置,加固杆外壁抵紧加固槽内壁形成固定,使固定杆不易脱离固定腔,实现相邻骨架的自动化连接,无需工作人员通过螺钉或者其它连接件对骨架进行连接,减少骨架的施工步骤,缩短对钢栈桥的施工周期,从而提高对钢栈桥的施工效率。
Steel trestle and construction method thereof
钢栈桥及其建造方法
PAN LIYANG (Autor:in) / JIANG XINGXUE (Autor:in)
09.07.2024
Patent
Elektronische Ressource
Chinesisch
Fabricated steel trestle structure and steel trestle construction method
Europäisches Patentamt | 2023
|Steel structure trestle and construction method thereof
Europäisches Patentamt | 2023
|