Enveloping type main transformer foundation construction method
The invention discloses an envelope type main transformer foundation construction method, and relates to the technical field of transformer substation main transformer foundations. The enveloping type main transformer foundation construction method comprises the following steps that S1, the length and width size of a main transformer foundation base and the depth of an oil pool are determined; s2, bottom layer pouring is conducted on the main transformer foundation base, a plurality of first connecting parts are reserved, pouring of a prefabricated part is conducted, and a first connecting part is connected to one side of the prefabricated part; s3, selective assembly of the prefabricated part on the main transformer foundation base is achieved through the first connecting part and the second connecting part; s4, a fence is arranged on the periphery of the main transformer foundation base in a surrounding mode, and a cable pipe is laid in the fence; and S5, top layer pouring is conducted on the upper portion of the main transformer foundation base in the fence. According to the enveloping type main transformer foundation construction method, the part of the main transformer foundation can be constructed in advance, the enveloping type main transformer foundation construction method is suitable for connection and installation between the main transformer foundation and the prefabricated part within the set range, rapid construction of the main transformer foundation is facilitated, the engineering efficiency is improved, and the engineering cost is reduced.
本发明公开了一种包络式主变基础施工方法,涉及变电站主变压器基础技术领域。本发明的包络式主变基础施工方法包括以下步骤:S1:确定主变基础底座的长宽尺寸和油池深度;S2:对主变基础底座进行底层浇筑并预留多个第一连接部,进行预制件的浇筑并在预制件的一侧连接第一连接件;S3:通过第一连接部和第二连接部实现预制件在主变基础底座上的选择装配;S4:在主变基础底座的周侧围设围挡,并在围挡内敷设电缆管;S5:在围挡内对主变基础底座上方进行顶层浇筑。本发明的包络式主变基础施工方法能够进行主变基础的部分进行预先施工,并适应于设定范围内主变基础与预制件之间的连接安装,便于主变基础的快速施工,提高工程效率并降低工程成本。
Enveloping type main transformer foundation construction method
The invention discloses an envelope type main transformer foundation construction method, and relates to the technical field of transformer substation main transformer foundations. The enveloping type main transformer foundation construction method comprises the following steps that S1, the length and width size of a main transformer foundation base and the depth of an oil pool are determined; s2, bottom layer pouring is conducted on the main transformer foundation base, a plurality of first connecting parts are reserved, pouring of a prefabricated part is conducted, and a first connecting part is connected to one side of the prefabricated part; s3, selective assembly of the prefabricated part on the main transformer foundation base is achieved through the first connecting part and the second connecting part; s4, a fence is arranged on the periphery of the main transformer foundation base in a surrounding mode, and a cable pipe is laid in the fence; and S5, top layer pouring is conducted on the upper portion of the main transformer foundation base in the fence. According to the enveloping type main transformer foundation construction method, the part of the main transformer foundation can be constructed in advance, the enveloping type main transformer foundation construction method is suitable for connection and installation between the main transformer foundation and the prefabricated part within the set range, rapid construction of the main transformer foundation is facilitated, the engineering efficiency is improved, and the engineering cost is reduced.
本发明公开了一种包络式主变基础施工方法,涉及变电站主变压器基础技术领域。本发明的包络式主变基础施工方法包括以下步骤:S1:确定主变基础底座的长宽尺寸和油池深度;S2:对主变基础底座进行底层浇筑并预留多个第一连接部,进行预制件的浇筑并在预制件的一侧连接第一连接件;S3:通过第一连接部和第二连接部实现预制件在主变基础底座上的选择装配;S4:在主变基础底座的周侧围设围挡,并在围挡内敷设电缆管;S5:在围挡内对主变基础底座上方进行顶层浇筑。本发明的包络式主变基础施工方法能够进行主变基础的部分进行预先施工,并适应于设定范围内主变基础与预制件之间的连接安装,便于主变基础的快速施工,提高工程效率并降低工程成本。
Enveloping type main transformer foundation construction method
一种包络式主变基础施工方法
ZHU GEJUN (Autor:in) / MENG FEI (Autor:in) / SHANG LINLIN (Autor:in)
12.07.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Main transformer cavity foundation construction method and main transformer cavity foundation
Europäisches Patentamt | 2023
|Steel-concrete combined assembly type main transformer foundation and construction method thereof
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2024
|Europäisches Patentamt | 2023
|Booster station main transformer foundation embedded part adjusting device and construction method
Europäisches Patentamt | 2024
|