Under-bridge low-clearance piling pontoon and construction method
The invention belongs to the technical field of bridge temporary support construction equipment, and particularly relates to an under-bridge low-clearance piling pontoon and a construction method. The device comprises a power equipment cabin, a balance cabin, a piling operation cabin, a support frame, a vibratory hammer, a counterweight unit, a vibratory hammer conveying mechanism and an operation room, the power equipment cabin, the balance cabin and the piling operation cabin are sequentially connected into a whole; the operation room is arranged on one side of the upper surface of the power equipment cabin; the supporting frame is vertically connected to the upper surfaces of the balance cabin and the power equipment cabin; the counterweight unit is connected to the side, close to the operation room, of the supporting frame. The supporting frame is connected with a longitudinal moving equipment group; the vibratory hammer conveying mechanism is connected to the upper surface of the power equipment cabin and located between the operation room and the supporting frame. The vibratory hammer conveying mechanism is connected with a vibratory hammer through a supporting frame, and the vibratory hammer is located on one side of the piling operation cabin. According to the method, convenience of bridge dismantling and transformation construction is guaranteed, the piling construction efficiency is improved, and the construction progress and the construction speed of erecting of the low-clearance steel pipe support under the bridge are guaranteed.
本发明属于桥梁临时支架施工设备技术领域,具体涉及一种桥下低净空打桩浮船及施工方法。本发明包括动力设备舱、平衡舱、打桩操作舱、支撑架、振动锤、配重单元、振动锤输送机构和操作间;动力设备舱、平衡舱和打桩操作舱依顺序连接为一体;操作间置于动力设备舱上表面的一侧;支撑架竖直连接在平衡舱和动力设备舱上表面;配重单元连接在支撑架靠近操作间一侧;支撑架上连接有纵移设备组;振动锤输送机构连接在动力设备舱上表面且位于操作间与支撑架之间;振动锤输送机构经支撑架与振动锤连接,振动锤位于打桩操作舱一侧。本发明保证了桥梁拆除、改造施工的便利,提高了打桩的施工效率,保证了施工进度和桥下低净空钢管支架搭设的施工速度。
Under-bridge low-clearance piling pontoon and construction method
The invention belongs to the technical field of bridge temporary support construction equipment, and particularly relates to an under-bridge low-clearance piling pontoon and a construction method. The device comprises a power equipment cabin, a balance cabin, a piling operation cabin, a support frame, a vibratory hammer, a counterweight unit, a vibratory hammer conveying mechanism and an operation room, the power equipment cabin, the balance cabin and the piling operation cabin are sequentially connected into a whole; the operation room is arranged on one side of the upper surface of the power equipment cabin; the supporting frame is vertically connected to the upper surfaces of the balance cabin and the power equipment cabin; the counterweight unit is connected to the side, close to the operation room, of the supporting frame. The supporting frame is connected with a longitudinal moving equipment group; the vibratory hammer conveying mechanism is connected to the upper surface of the power equipment cabin and located between the operation room and the supporting frame. The vibratory hammer conveying mechanism is connected with a vibratory hammer through a supporting frame, and the vibratory hammer is located on one side of the piling operation cabin. According to the method, convenience of bridge dismantling and transformation construction is guaranteed, the piling construction efficiency is improved, and the construction progress and the construction speed of erecting of the low-clearance steel pipe support under the bridge are guaranteed.
本发明属于桥梁临时支架施工设备技术领域,具体涉及一种桥下低净空打桩浮船及施工方法。本发明包括动力设备舱、平衡舱、打桩操作舱、支撑架、振动锤、配重单元、振动锤输送机构和操作间;动力设备舱、平衡舱和打桩操作舱依顺序连接为一体;操作间置于动力设备舱上表面的一侧;支撑架竖直连接在平衡舱和动力设备舱上表面;配重单元连接在支撑架靠近操作间一侧;支撑架上连接有纵移设备组;振动锤输送机构连接在动力设备舱上表面且位于操作间与支撑架之间;振动锤输送机构经支撑架与振动锤连接,振动锤位于打桩操作舱一侧。本发明保证了桥梁拆除、改造施工的便利,提高了打桩的施工效率,保证了施工进度和桥下低净空钢管支架搭设的施工速度。
Under-bridge low-clearance piling pontoon and construction method
一种桥下低净空打桩浮船及施工方法
XU ZHIXING (Autor:in) / MENG FANCHUAN (Autor:in) / ZHAO GANG (Autor:in)
16.07.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method for low-clearance hydraulic hammering piling and piling machine
Europäisches Patentamt | 2023
|Modular intelligent pontoon bridge device and pontoon bridge building method
Europäisches Patentamt | 2021
|UNDERWATER PONTOON BRIDGE AND METHOD OF ITS CONSTRUCTION
Europäisches Patentamt | 2019
|