High-standard farmland ridge reinforcing measure and construction method thereof
The invention provides a high-standard farmland ridge reinforcement measure and a construction method thereof, and the method comprises the following steps: before the construction of a ridge, a total station is used for releasing the center line of the ridge; one iron nail is driven in along the center line at certain intervals, and the side boundary of the field ridge is released according to each iron nail; surface sundries in the newly-built field ridge range are removed; pits generated by cleaning the sundries are densely filled with natural cohesive soil; the timber pile is pressed into the leveled and rolled soil; weaving bamboo canes on the timber piles on the two sides of the field ridge and fixing the bamboo canes; the outer sides of the double-row timber piles are backfilled with immature soil in a layered mode, the inner sides of the double-row timber piles are backfilled with semi-solidified soil in a layered mode till the designed height is reached, and finally building of the field ridge is completed. The reinforcement measure for the field ridge of the high-standard farmland and the construction method of the reinforcement measure can be suitable for the conditions that a common soil field ridge is prone to collapse and cracking and the compaction degree is insufficient in the high-standard farmland construction, the strength and stability of the field ridge can be guaranteed, and meanwhile semi-solidified soil cannot pollute the environment and soil.
本发明提供一种高标准农田田坎加固措施及其施工方法,包括以下步骤:在田坎施工之前,用全站仪放出田坎的中心线;沿中心线每隔一定距离打入一根铁钉,根据每个铁钉,分别放出田坎的边线;清除新建田坎范围内地表杂物;清理杂物产生的坑采用自然粘性土换填密实;将木桩压入整平碾压后的土壤中;将竹条分别编制在田坎两侧木桩上并固定;在双排木桩外侧分层回填生土,在双排木桩内侧分层回填半固化土,直至达到设计高度,最终完成田坎的修筑。本发明提供的用于高标准农田田坎加固措施及其施工方法,能够适用于高标准农田建设中普通土质田坎容易垮塌开裂且压实度不够的情况,能够保证田坎强度和稳定的同时,半固化土不会对环境和土壤造成污染。
High-standard farmland ridge reinforcing measure and construction method thereof
The invention provides a high-standard farmland ridge reinforcement measure and a construction method thereof, and the method comprises the following steps: before the construction of a ridge, a total station is used for releasing the center line of the ridge; one iron nail is driven in along the center line at certain intervals, and the side boundary of the field ridge is released according to each iron nail; surface sundries in the newly-built field ridge range are removed; pits generated by cleaning the sundries are densely filled with natural cohesive soil; the timber pile is pressed into the leveled and rolled soil; weaving bamboo canes on the timber piles on the two sides of the field ridge and fixing the bamboo canes; the outer sides of the double-row timber piles are backfilled with immature soil in a layered mode, the inner sides of the double-row timber piles are backfilled with semi-solidified soil in a layered mode till the designed height is reached, and finally building of the field ridge is completed. The reinforcement measure for the field ridge of the high-standard farmland and the construction method of the reinforcement measure can be suitable for the conditions that a common soil field ridge is prone to collapse and cracking and the compaction degree is insufficient in the high-standard farmland construction, the strength and stability of the field ridge can be guaranteed, and meanwhile semi-solidified soil cannot pollute the environment and soil.
本发明提供一种高标准农田田坎加固措施及其施工方法,包括以下步骤:在田坎施工之前,用全站仪放出田坎的中心线;沿中心线每隔一定距离打入一根铁钉,根据每个铁钉,分别放出田坎的边线;清除新建田坎范围内地表杂物;清理杂物产生的坑采用自然粘性土换填密实;将木桩压入整平碾压后的土壤中;将竹条分别编制在田坎两侧木桩上并固定;在双排木桩外侧分层回填生土,在双排木桩内侧分层回填半固化土,直至达到设计高度,最终完成田坎的修筑。本发明提供的用于高标准农田田坎加固措施及其施工方法,能够适用于高标准农田建设中普通土质田坎容易垮塌开裂且压实度不够的情况,能够保证田坎强度和稳定的同时,半固化土不会对环境和土壤造成污染。
High-standard farmland ridge reinforcing measure and construction method thereof
一种高标准农田田坎加固措施及其施工方法
GONG WENWU (Autor:in) / BAO HAILIANG (Autor:in) / DONG WANLONG (Autor:in) / ZHANG CHUNSHENG (Autor:in) / RAN PENGLIN (Autor:in) / LIU XING (Autor:in) / XIANG XINGDONG (Autor:in)
19.07.2024
Patent
Elektronische Ressource
Chinesisch
High-standard farmland ditch cleaning and construction method
Europäisches Patentamt | 2024
|High-standard farmland channel construction method and structure
Europäisches Patentamt | 2020
|Reinforcing construction method for reverse ridge formwork
Europäisches Patentamt | 2024
|High-standard farmland channel cleaning device and construction method
Europäisches Patentamt | 2023
|