Steam turbine foundation secondary grouting permanent formwork structure and construction method
The invention provides a steam turbine foundation secondary grouting permanent formwork structure and a construction method. The construction method comprises the steps that a center line and an elevation control line of a permanent formwork removal-free formwork are set out on an equipment foundation; processing and manufacturing the permanent formwork removal-free formwork; preliminary positioning is conducted according to the center line and the elevation control line, and the permanent formwork-removal-free formwork and the foundation steel bars are welded and fixed through support steel bars; the turbine foundation side mold is reinforced; concrete pouring is conducted on the steam turbine foundation; and a permanent formwork-removal-free formwork is adopted as a formwork for secondary pouring, secondary pouring of the equipment foundation grouting material is conducted, and a secondary grouting layer is formed. According to the method, the position of the permanent formwork-removal-free formwork is determined according to the installation position of the steam turbine, the permanent formwork-removal-free formwork is installed, the permanent formwork-removal-free formwork serves as a formwork for secondary grouting, and secondary pouring of equipment foundation grouting materials is conducted after steam turbine equipment is installed.
本发明提供了一种汽轮机基础二次灌浆永久模板构造及施工方法,该施工方法包括:在设备基础上放出永久免拆模模板的中心线和标高控制线;对永久免拆模模板进行加工制作;根据中心线和标高控制线进行初步定位,使用支架钢筋将永久免拆模模板与基础钢筋焊接固定;对汽轮机基础侧模进行加固;对汽轮机基础进行混凝土的浇筑;采用永久免拆模模板作为二次浇筑的模板,进行设备基础灌浆料的二次浇筑,形成二次灌浆层。本发明根据汽轮机安装位置确定永久免拆模模板的位置,对永久免拆模模板进行安装,通过永久免拆模模板作为二次灌浆的模板,在汽轮机设备安装完毕后进行设备基础灌浆料的二次浇筑。
Steam turbine foundation secondary grouting permanent formwork structure and construction method
The invention provides a steam turbine foundation secondary grouting permanent formwork structure and a construction method. The construction method comprises the steps that a center line and an elevation control line of a permanent formwork removal-free formwork are set out on an equipment foundation; processing and manufacturing the permanent formwork removal-free formwork; preliminary positioning is conducted according to the center line and the elevation control line, and the permanent formwork-removal-free formwork and the foundation steel bars are welded and fixed through support steel bars; the turbine foundation side mold is reinforced; concrete pouring is conducted on the steam turbine foundation; and a permanent formwork-removal-free formwork is adopted as a formwork for secondary pouring, secondary pouring of the equipment foundation grouting material is conducted, and a secondary grouting layer is formed. According to the method, the position of the permanent formwork-removal-free formwork is determined according to the installation position of the steam turbine, the permanent formwork-removal-free formwork is installed, the permanent formwork-removal-free formwork serves as a formwork for secondary grouting, and secondary pouring of equipment foundation grouting materials is conducted after steam turbine equipment is installed.
本发明提供了一种汽轮机基础二次灌浆永久模板构造及施工方法,该施工方法包括:在设备基础上放出永久免拆模模板的中心线和标高控制线;对永久免拆模模板进行加工制作;根据中心线和标高控制线进行初步定位,使用支架钢筋将永久免拆模模板与基础钢筋焊接固定;对汽轮机基础侧模进行加固;对汽轮机基础进行混凝土的浇筑;采用永久免拆模模板作为二次浇筑的模板,进行设备基础灌浆料的二次浇筑,形成二次灌浆层。本发明根据汽轮机安装位置确定永久免拆模模板的位置,对永久免拆模模板进行安装,通过永久免拆模模板作为二次灌浆的模板,在汽轮机设备安装完毕后进行设备基础灌浆料的二次浇筑。
Steam turbine foundation secondary grouting permanent formwork structure and construction method
一种汽轮机基础二次灌浆永久模板构造及施工方法
LI HUAXING (Autor:in) / MA RUJIAN (Autor:in) / ZHANG HAO (Autor:in) / ZHANG YONGBO (Autor:in) / ZHANG ZELIN (Autor:in) / ZHANG XINGYUAN (Autor:in)
06.08.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2015
|Europäisches Patentamt | 2016
|FOUNDATION FORMWORK STRUCTURE AND FOUNDATION FORMWORK METHOD
Europäisches Patentamt | 2024
|