Ballast box of box girder spliced wide bridge and construction method
The invention relates to a bridge structure, in particular to a box girder spliced wide bridge ballasting box and a construction method.The box girder spliced wide bridge ballasting box comprises a bottom plate, a plurality of partition plates are installed at the top of the bottom plate, a web is installed on one side of the bottom plate, and the side face, facing the partition plates, of the web is connected with one side of each partition plate; the ballasting structure forms a plurality of separation spaces with openings in the tops and the side faces in the extending direction of the bottom plate; the web plate is higher than the partition plate, and the opening side portions of the ballasting structure are connected with a bridge body to be constructed to form a cavity filled with ballasting materials; the ballasting structure can serve as a temporary structure, can balance bridge loads and can also prevent overturning, the ballasting structure is safe and convenient to construct, and after construction is finished, the ballasting structure can serve as a permanent structure to bear loads of vehicles on the upper portion together with an existing bridge.
本发明涉及桥梁结构,尤其涉及一种箱梁拼宽桥压重箱及施工方法,包括底板,所述底板顶部安装有若干隔板,所述底板一侧安装有腹板,所述腹板朝向所述隔板的侧面分别与每个所述隔板一侧连接,使得所述压重结构沿着所述底板的延伸方向形成若干顶部和侧面开口的分隔空间;所述腹板高度高于隔板的高度,将压重结构的开口侧部位分别与待施工桥体连接,形成填充压重材料空腔;本发明既可作为临时结构既可平衡桥梁荷载,也可防止倾覆,该压重结构施工时安全、便捷,施工结束后,又可作为永久结构与既有桥梁一同承载上部车辆荷载。
Ballast box of box girder spliced wide bridge and construction method
The invention relates to a bridge structure, in particular to a box girder spliced wide bridge ballasting box and a construction method.The box girder spliced wide bridge ballasting box comprises a bottom plate, a plurality of partition plates are installed at the top of the bottom plate, a web is installed on one side of the bottom plate, and the side face, facing the partition plates, of the web is connected with one side of each partition plate; the ballasting structure forms a plurality of separation spaces with openings in the tops and the side faces in the extending direction of the bottom plate; the web plate is higher than the partition plate, and the opening side portions of the ballasting structure are connected with a bridge body to be constructed to form a cavity filled with ballasting materials; the ballasting structure can serve as a temporary structure, can balance bridge loads and can also prevent overturning, the ballasting structure is safe and convenient to construct, and after construction is finished, the ballasting structure can serve as a permanent structure to bear loads of vehicles on the upper portion together with an existing bridge.
本发明涉及桥梁结构,尤其涉及一种箱梁拼宽桥压重箱及施工方法,包括底板,所述底板顶部安装有若干隔板,所述底板一侧安装有腹板,所述腹板朝向所述隔板的侧面分别与每个所述隔板一侧连接,使得所述压重结构沿着所述底板的延伸方向形成若干顶部和侧面开口的分隔空间;所述腹板高度高于隔板的高度,将压重结构的开口侧部位分别与待施工桥体连接,形成填充压重材料空腔;本发明既可作为临时结构既可平衡桥梁荷载,也可防止倾覆,该压重结构施工时安全、便捷,施工结束后,又可作为永久结构与既有桥梁一同承载上部车辆荷载。
Ballast box of box girder spliced wide bridge and construction method
一种箱梁拼宽桥压重箱及施工方法
ZHAO ZHAN (Autor:in) / JIAO ZHONGWEI (Autor:in) / HAN MINGTAO (Autor:in) / LIU JIANGJIANG (Autor:in) / YU HAIPING (Autor:in) / CAO GUANGFEI (Autor:in) / LI XIAOMENG (Autor:in) / HAN ZHIPAN (Autor:in)
06.09.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Spliced girder bridge and construction method thereof
Europäisches Patentamt | 2015
|PSC Prestressed Concrete Spliced Girder Bridge and Construction method thereof
Europäisches Patentamt | 2021
|Spliced I-Girder Concrete Bridge System
NTIS | 2003
|Construction method for erecting prefabricated box girder of spliced and widened bridge
Europäisches Patentamt | 2022
|PSC PSC Prestressed Concrete Spliced Girder Bridge and Construction method of thereof