Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Basement bottom plate tower crane foundation hole gushing water blocking structure and construction system
The invention relates to the technical field of building construction, in particular to a basement bottom plate tower crane foundation hole gushing water blocking structure and a construction system, comprising a blind pipe assembly 1, a water stop steel sleeve assembly 2 and a water pumping pipe 3; a broken stone hardcore 802 is laid on the top of the tower crane foundation 801 and plays a role in gap drainage. A blind pipe assembly 1 is buried in the broken stone hardcore 802, an opening in the top of the blind pipe assembly 1 faces upwards, and the blind pipe assembly 1 is wrapped with geotechnical cloth 803, so that soil particles of a basement bottom plate are prevented from being taken away by later water pumping; and geotechnical cloth 803 is laid on the broken stone hardcore 802 and plays a role in isolation. And through multi-layer waterproof measures and grouting hardening treatment, the water burst problem of the basement bottom plate tower crane foundation hole is effectively solved.
本发明涉及建筑施工技术领域,尤其涉及一种地下室底板塔吊基础洞口涌水封堵结构及施工体系,包括盲管组件1、止水钢套管组件2和抽水管3;塔吊基础801顶部铺设有碎石垫层802,起到缝隙排水作用;并在碎石垫层802中埋设有盲管组件1,盲管组件1顶部的开口朝上,采用土工布803包裹,防止后期抽水带走地下室底板土粒;碎石垫层802上铺设有土工布803,起到隔离作用。并通过多层防水措施和注浆硬化处理,有效封堵地下室底板塔吊基础洞口的涌水问题。
Basement bottom plate tower crane foundation hole gushing water blocking structure and construction system
The invention relates to the technical field of building construction, in particular to a basement bottom plate tower crane foundation hole gushing water blocking structure and a construction system, comprising a blind pipe assembly 1, a water stop steel sleeve assembly 2 and a water pumping pipe 3; a broken stone hardcore 802 is laid on the top of the tower crane foundation 801 and plays a role in gap drainage. A blind pipe assembly 1 is buried in the broken stone hardcore 802, an opening in the top of the blind pipe assembly 1 faces upwards, and the blind pipe assembly 1 is wrapped with geotechnical cloth 803, so that soil particles of a basement bottom plate are prevented from being taken away by later water pumping; and geotechnical cloth 803 is laid on the broken stone hardcore 802 and plays a role in isolation. And through multi-layer waterproof measures and grouting hardening treatment, the water burst problem of the basement bottom plate tower crane foundation hole is effectively solved.
本发明涉及建筑施工技术领域,尤其涉及一种地下室底板塔吊基础洞口涌水封堵结构及施工体系,包括盲管组件1、止水钢套管组件2和抽水管3;塔吊基础801顶部铺设有碎石垫层802,起到缝隙排水作用;并在碎石垫层802中埋设有盲管组件1,盲管组件1顶部的开口朝上,采用土工布803包裹,防止后期抽水带走地下室底板土粒;碎石垫层802上铺设有土工布803,起到隔离作用。并通过多层防水措施和注浆硬化处理,有效封堵地下室底板塔吊基础洞口的涌水问题。
Basement bottom plate tower crane foundation hole gushing water blocking structure and construction system
一种地下室底板塔吊基础洞口涌水封堵结构及施工体系
XU ZHIPENG (Autor:in) / GONG JIANJUN (Autor:in) / HAN LIU (Autor:in) / ZHANG WENBIN (Autor:in) / YU HONGXIANG (Autor:in) / CHEN YUANZHONG (Autor:in) / CHENG XIAOMING (Autor:in) / XIONG XUEGANG (Autor:in) / YOU RUI (Autor:in) / GUO JUN (Autor:in)
10.09.2024
Patent
Elektronische Ressource
Chinesisch
Tower crane foundation construction method based on basement bottom plate
Europäisches Patentamt | 2024
|Structure construction method for tower crane foundation serving as basement bottom plate
Europäisches Patentamt | 2016
|Anchor cable hole gushing water blocking construction structure
Europäisches Patentamt | 2024
|