Construction method for cast-in-place straining beam constructional column of external wall thermal insulation building block
The invention relates to the technical field of constructional engineering, in particular to a construction method of an external wall thermal insulation building block cast-in-place tie beam constructional column, which comprises the following steps: firstly, performing accurate layout on a thermal insulation integrated plate on the outer side of a thermal insulation building block to ensure the mold matching size and reinforcing quality of a cast-in-place tie beam and a constructional column; steel bar planting positions of a constructional column and a tie beam are reserved in advance, after steel bar planting is completed, a reinforcement cage is bound, a heat preservation integrated plate is used on the outer side of a heat preservation building block for mold matching, wood formworks are used on the other side faces of the heat preservation building block for mold matching, and after concrete pouring is completed, the wood formworks on the inner side are removed, and the heat preservation integrated plate on the outer side is reserved; the construction method has the beneficial effects that integrated construction of cast-in-place part heat preservation and heat preservation building block external heat preservation is achieved, and the cold bridge phenomenon is avoided.
本发明涉及建筑工程技术领域,具体为一种外墙保温砌块现浇系梁构造柱施工方法,包括:首先对保温砌块外侧的保温一体板进行精确排版,保证现浇系梁和构造柱的配模尺寸和加固质量,在大跨度门窗洞口节点保温砌块砌筑过程中,提前预留构造柱和系梁植筋位置,待植筋完成后,进行钢筋笼的绑扎,保温砌块外侧使用保温一体板配模,保温砌块其余侧面使用木模板配模,混凝土浇筑完成后,对内侧木模板进行拆除,外侧保温一体板进行保留;有益效果为:实现现浇部位保温与保温砌块外保温整体化施工,避免冷桥现象的出现。
Construction method for cast-in-place straining beam constructional column of external wall thermal insulation building block
The invention relates to the technical field of constructional engineering, in particular to a construction method of an external wall thermal insulation building block cast-in-place tie beam constructional column, which comprises the following steps: firstly, performing accurate layout on a thermal insulation integrated plate on the outer side of a thermal insulation building block to ensure the mold matching size and reinforcing quality of a cast-in-place tie beam and a constructional column; steel bar planting positions of a constructional column and a tie beam are reserved in advance, after steel bar planting is completed, a reinforcement cage is bound, a heat preservation integrated plate is used on the outer side of a heat preservation building block for mold matching, wood formworks are used on the other side faces of the heat preservation building block for mold matching, and after concrete pouring is completed, the wood formworks on the inner side are removed, and the heat preservation integrated plate on the outer side is reserved; the construction method has the beneficial effects that integrated construction of cast-in-place part heat preservation and heat preservation building block external heat preservation is achieved, and the cold bridge phenomenon is avoided.
本发明涉及建筑工程技术领域,具体为一种外墙保温砌块现浇系梁构造柱施工方法,包括:首先对保温砌块外侧的保温一体板进行精确排版,保证现浇系梁和构造柱的配模尺寸和加固质量,在大跨度门窗洞口节点保温砌块砌筑过程中,提前预留构造柱和系梁植筋位置,待植筋完成后,进行钢筋笼的绑扎,保温砌块外侧使用保温一体板配模,保温砌块其余侧面使用木模板配模,混凝土浇筑完成后,对内侧木模板进行拆除,外侧保温一体板进行保留;有益效果为:实现现浇部位保温与保温砌块外保温整体化施工,避免冷桥现象的出现。
Construction method for cast-in-place straining beam constructional column of external wall thermal insulation building block
一种外墙保温砌块现浇系梁构造柱施工方法
ZHANG HEYUN (Autor:in) / HOU BOFENG (Autor:in) / ZHEN RUIHENG (Autor:in) / WANG SHUAISHUAI (Autor:in) / LI XIAOBIN (Autor:in)
10.09.2024
Patent
Elektronische Ressource
Chinesisch
Europäisches Patentamt | 2023
|Self-insulation wall constructional column and insulation brick integrated construction method
Europäisches Patentamt | 2024
|Building block structure of masonry filler wall constructional column and construction method
Europäisches Patentamt | 2024
|External wall thermal insulation building block and external wall thermal insulation system
Europäisches Patentamt | 2023
|Constructional engineering constructional column structure and wall building method
Europäisches Patentamt | 2021
|