Integrated pile feeder and pile sinking construction method
The invention relates to an integrated pile feeder which comprises a pile feeder body and an upper pile cap, the pile feeder body is sleeved with a baffle, the other end of the pile feeder body is provided with a pile sleeve, and the pile sleeve is used for sleeving a steel pipe pile; the pile feeder body is sleeved with the upper pile cap, the upper pile cap is in bolted connection with the baffle, a pile hammer mounting hole is formed in the top of the upper pile cap, and first bolt holes are formed in the periphery of the pile hammer mounting hole. The top end of the pile feeder body is sleeved with the baffle, the baffle is in bolted connection with the upper pile cap, and the upper pile cap is in bolted connection with the pile hammer, so that the integrated pile feeder is directly connected with the pile hammer, and meanwhile, the axis direction of the integrated pile feeder is consistent with that of the pile hammer; the axial direction of the integrated pile feeder is consistent with that of the steel pipe pile, the energy transmission efficiency in the pile sinking process is greatly improved, and the technical problem that in the related technology, due to the fact that the energy transmission efficiency is low in the pile sinking process, it cannot be guaranteed that an inclined pile is sunk to the designed elevation and reaches the designed angle is solved.
本申请涉及一种一体式送桩器,其包括:送桩器本体和上桩帽,送桩器本体外套设有挡板,送桩器本体的另一端设置有桩套筒,桩套筒用于套装钢管桩;上桩帽套设于送桩器本体,且上桩帽与挡板栓接,上桩帽的顶部设置有桩锤安装孔,桩锤安装孔的四周设置有第一螺栓孔。通过在送桩器本体的顶端套设挡板,挡板栓接上桩帽,上桩帽与桩锤栓接,使一体式送桩器直接连接桩锤,同时一体式送桩器与桩锤的轴线方向一致,通过在送桩器本体的底端设置桩套筒,桩套筒套装钢管桩,使一体式送桩器与钢管桩的轴线方向一致,大幅提高沉桩过程中的能量传递效率,解决了相关技术中在沉桩过程中因能量传递效率低,无法保证斜桩沉桩至设计标高和达到设计角度的技术问题。
Integrated pile feeder and pile sinking construction method
The invention relates to an integrated pile feeder which comprises a pile feeder body and an upper pile cap, the pile feeder body is sleeved with a baffle, the other end of the pile feeder body is provided with a pile sleeve, and the pile sleeve is used for sleeving a steel pipe pile; the pile feeder body is sleeved with the upper pile cap, the upper pile cap is in bolted connection with the baffle, a pile hammer mounting hole is formed in the top of the upper pile cap, and first bolt holes are formed in the periphery of the pile hammer mounting hole. The top end of the pile feeder body is sleeved with the baffle, the baffle is in bolted connection with the upper pile cap, and the upper pile cap is in bolted connection with the pile hammer, so that the integrated pile feeder is directly connected with the pile hammer, and meanwhile, the axis direction of the integrated pile feeder is consistent with that of the pile hammer; the axial direction of the integrated pile feeder is consistent with that of the steel pipe pile, the energy transmission efficiency in the pile sinking process is greatly improved, and the technical problem that in the related technology, due to the fact that the energy transmission efficiency is low in the pile sinking process, it cannot be guaranteed that an inclined pile is sunk to the designed elevation and reaches the designed angle is solved.
本申请涉及一种一体式送桩器,其包括:送桩器本体和上桩帽,送桩器本体外套设有挡板,送桩器本体的另一端设置有桩套筒,桩套筒用于套装钢管桩;上桩帽套设于送桩器本体,且上桩帽与挡板栓接,上桩帽的顶部设置有桩锤安装孔,桩锤安装孔的四周设置有第一螺栓孔。通过在送桩器本体的顶端套设挡板,挡板栓接上桩帽,上桩帽与桩锤栓接,使一体式送桩器直接连接桩锤,同时一体式送桩器与桩锤的轴线方向一致,通过在送桩器本体的底端设置桩套筒,桩套筒套装钢管桩,使一体式送桩器与钢管桩的轴线方向一致,大幅提高沉桩过程中的能量传递效率,解决了相关技术中在沉桩过程中因能量传递效率低,无法保证斜桩沉桩至设计标高和达到设计角度的技术问题。
Integrated pile feeder and pile sinking construction method
一种一体式送桩器及沉桩施工方法
JIA WEIZHONG (Autor:in) / WANG YINFENG (Autor:in) / HAYASHI NOBORU (Autor:in) / ZHANG YIXIN (Autor:in) / YU YUNFENG (Autor:in) / ZHOU GONGJIAN (Autor:in) / YU HONGWEI (Autor:in) / JIA ZHIJIE (Autor:in) / ZHOU QIANGQIANG (Autor:in)
24.09.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Pile feeder structure for assisting pile sinking construction
Europäisches Patentamt | 2024
|Wind power single pile, pile sinking construction device and pile sinking construction method
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2020
|Guide hole and pile sinking integrated prefabricated pipe pile construction method
Europäisches Patentamt | 2023
|