Assembling method for prefabricated temporary tool box wall
The invention discloses an assembling method for a prefabricated temporary tool box wall. The assembling method comprises the following steps that soil body reinforcement and guide wall construction are conducted; the permanent diaphragm wall is lowered to the temporary fixed elevation position; the tool box wall is hoisted and installed to form an integral wall; fixing of the permanent diaphragm wall is removed, and after the integral wall is lowered to the elevation, the integral wall is fixed; and the steps are repeated, and integral wall assembly of one line production is completed. Grouting is carried out on the integral wall in a line production range, and after the design requirement is met, a tool box wall in a next line production range is assembled; foundation pit excavation, main body construction and soil body backfilling are conducted; and the temporary tool box wall is pulled out and backfilled to the ground, and construction is completed. The permanent underground diaphragm wall and the tool box wall are combined together to jointly play a role in enclosure, the temporary tool box wall is pulled out after construction is finished, the work of chiseling away existing underground obstacles in later municipal pipeline construction is reduced, the temporary tool box wall can be reused, construction is convenient and fast, investment is saved, and environmental protection is achieved.
本发明公开了一种预制临时工具箱墙的装配方法,包括以下步骤:进行土体加固,导墙施做;下放永久地连墙到临时固定标高位置;吊送、安装工具箱墙,形成整体墙;撤走永久地连墙的固定,下放整体墙至标高后,进行整体墙固定;重复上述步骤,完成一个流水作业的整体墙装配;对一个流水作业范围内的整体墙进行注浆,达到设计要求后,装配下一流水作业范围内的工具箱墙;进行基坑开挖、主体施工、土体回填;拔出临时工具箱墙,回填至地面,完成施工。本发明将永久地连墙、工具箱墙组合在一起共同起到围护作用,施工结束拔出临时工具箱墙,减少了后期市政管线施工对既有地下障碍物的凿除工作,且临时工具箱墙可重复利用,施工便捷、节省投资、绿色环保。
Assembling method for prefabricated temporary tool box wall
The invention discloses an assembling method for a prefabricated temporary tool box wall. The assembling method comprises the following steps that soil body reinforcement and guide wall construction are conducted; the permanent diaphragm wall is lowered to the temporary fixed elevation position; the tool box wall is hoisted and installed to form an integral wall; fixing of the permanent diaphragm wall is removed, and after the integral wall is lowered to the elevation, the integral wall is fixed; and the steps are repeated, and integral wall assembly of one line production is completed. Grouting is carried out on the integral wall in a line production range, and after the design requirement is met, a tool box wall in a next line production range is assembled; foundation pit excavation, main body construction and soil body backfilling are conducted; and the temporary tool box wall is pulled out and backfilled to the ground, and construction is completed. The permanent underground diaphragm wall and the tool box wall are combined together to jointly play a role in enclosure, the temporary tool box wall is pulled out after construction is finished, the work of chiseling away existing underground obstacles in later municipal pipeline construction is reduced, the temporary tool box wall can be reused, construction is convenient and fast, investment is saved, and environmental protection is achieved.
本发明公开了一种预制临时工具箱墙的装配方法,包括以下步骤:进行土体加固,导墙施做;下放永久地连墙到临时固定标高位置;吊送、安装工具箱墙,形成整体墙;撤走永久地连墙的固定,下放整体墙至标高后,进行整体墙固定;重复上述步骤,完成一个流水作业的整体墙装配;对一个流水作业范围内的整体墙进行注浆,达到设计要求后,装配下一流水作业范围内的工具箱墙;进行基坑开挖、主体施工、土体回填;拔出临时工具箱墙,回填至地面,完成施工。本发明将永久地连墙、工具箱墙组合在一起共同起到围护作用,施工结束拔出临时工具箱墙,减少了后期市政管线施工对既有地下障碍物的凿除工作,且临时工具箱墙可重复利用,施工便捷、节省投资、绿色环保。
Assembling method for prefabricated temporary tool box wall
一种预制临时工具箱墙的装配方法
XU ZHENYAN (Autor:in) / ZHANG CHUNLEI (Autor:in) / ZHANG PENG (Autor:in) / MA ZHENHAI (Autor:in) / ZHANG YUHUA (Autor:in) / WANG DALIN (Autor:in) / CUI TAO (Autor:in) / SONG RAN (Autor:in) / SONG LEYANG (Autor:in) / XU YUNHE (Autor:in)
11.10.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Europäisches Patentamt | 2016
|Assembling structure and assembling method of prefabricated wall panel
Europäisches Patentamt | 2024
|Assembling type retaining wall prefabricated part and assembling method thereof
Europäisches Patentamt | 2021
|Europäisches Patentamt | 2024
|