Soft foundation automatic construction system and construction method
According to the automatic construction system and method for the soft foundation, overall planning is conducted on a construction project through a pile construction supervision platform, pile types and pile positions are determined, the total construction amount and the construction amount of all pile machines are planned, early warning configuration is conducted, and early warning information and project progress information are counted; performing early warning processing and broadcasting on the early warning condition according to the early warning processing strategy; the method comprises the following steps: performing action control on a pile machine at a construction site through a front-end controller, locally storing and uploading all sensor detection data and control records of a current pile, performing real-time monitoring on the sensor detection data according to early warning configuration, and performing early warning treatment and broadcasting on an early warning condition according to an early warning treatment strategy when the early warning condition occurs; the total construction process, the single pile machine construction record and the single pile production construction record are looked up and displayed through the mobile terminal, and early warning processing and broadcasting are conducted on the early warning condition according to the early warning processing strategy; and when the early-warning condition is completely handled according to the early-warning handling strategy, an early-warning closed loop is realized.
本发明公开了一种软基自动化施工系统及施工方法,通过桩施工监管平台对施工项目进行整体规划,确定桩类型和桩位置、规划总施工量和各桩机施工量、进行预警配置、统计预警信息及工程进度信息,根据预警处置策略对预警情况进行预警处置并广播;通过前端控制器在施工现场对桩机进行动作操控,本地存储并上传当前桩的所有传感器检测数据和操控记录,根据预警配置对传感器检测数据进行实时监测,在发生预警情况时根据预警处置策略对预警情况进行预警处置并广播;通过移动端对总施工进程、单个桩机施工记录和单个桩生产施工记录进行查阅和显示,根据预警处置策略对预警情况进行预警处置并广播;当预警情况根据预警处置策略完成全部处置则实现预警闭环。
Soft foundation automatic construction system and construction method
According to the automatic construction system and method for the soft foundation, overall planning is conducted on a construction project through a pile construction supervision platform, pile types and pile positions are determined, the total construction amount and the construction amount of all pile machines are planned, early warning configuration is conducted, and early warning information and project progress information are counted; performing early warning processing and broadcasting on the early warning condition according to the early warning processing strategy; the method comprises the following steps: performing action control on a pile machine at a construction site through a front-end controller, locally storing and uploading all sensor detection data and control records of a current pile, performing real-time monitoring on the sensor detection data according to early warning configuration, and performing early warning treatment and broadcasting on an early warning condition according to an early warning treatment strategy when the early warning condition occurs; the total construction process, the single pile machine construction record and the single pile production construction record are looked up and displayed through the mobile terminal, and early warning processing and broadcasting are conducted on the early warning condition according to the early warning processing strategy; and when the early-warning condition is completely handled according to the early-warning handling strategy, an early-warning closed loop is realized.
本发明公开了一种软基自动化施工系统及施工方法,通过桩施工监管平台对施工项目进行整体规划,确定桩类型和桩位置、规划总施工量和各桩机施工量、进行预警配置、统计预警信息及工程进度信息,根据预警处置策略对预警情况进行预警处置并广播;通过前端控制器在施工现场对桩机进行动作操控,本地存储并上传当前桩的所有传感器检测数据和操控记录,根据预警配置对传感器检测数据进行实时监测,在发生预警情况时根据预警处置策略对预警情况进行预警处置并广播;通过移动端对总施工进程、单个桩机施工记录和单个桩生产施工记录进行查阅和显示,根据预警处置策略对预警情况进行预警处置并广播;当预警情况根据预警处置策略完成全部处置则实现预警闭环。
Soft foundation automatic construction system and construction method
一种软基自动化施工系统及施工方法
ZHANG QING (Autor:in) / JIN XIN (Autor:in) / NI SIJIE (Autor:in) / GONG WEIAN (Autor:in) / YIN XINGEN (Autor:in) / DONG HUI (Autor:in) / WANG PENGCHENG (Autor:in) / HAO HAN (Autor:in) / LUO JIE (Autor:in)
26.11.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
/
G01D
MEASURING NOT SPECIALLY ADAPTED FOR A SPECIFIC VARIABLE
,
Anzeigen oder Aufzeichnen in Verbindung mit Messen allgemein
/
G06F
ELECTRIC DIGITAL DATA PROCESSING
,
Elektrische digitale Datenverarbeitung
/
G06Q
Datenverarbeitungssysteme oder -verfahren, besonders angepasst an verwaltungstechnische, geschäftliche, finanzielle oder betriebswirtschaftliche Zwecke, sowie an geschäftsbezogene Überwachungs- oder Voraussagezwecke
,
DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES
Soft foundation reinforcing system and construction method
Europäisches Patentamt | 2024
|Soft foundation building foundation structure and construction method
Europäisches Patentamt | 2021
|