The invention discloses a secondary structure preposed construction method which comprises the following steps: step 1, positioning and paying off, binding steel bars, pre-burying water and electricity pipes and boxes, anchoring a steel bar mesh into a primary structure beam column wall, preventing the upper end of the steel bar mesh from being anchored into a beam, and preventing the steel bar mesh from being bent after the beam is stressed to cause cracks of a foam concrete wall; the upper end of the reinforcing mesh is flush with the bottom of the extruded sheet; 2, a formwork of a primary structure and a formwork of a secondary structure are erected at the same time; 3, a secondary structure is poured; the secondary structure is a foam concrete wall; fourthly, after the foam concrete wall in the third step is finally set, structural concrete is poured again; step 5, removing the mold; and 6, removing the steel pipe bracket after the mold is removed. The primary structure and the secondary structure are constructed and completed at the same time, seamless connection is achieved, a long process interval is avoided, the construction period is greatly shortened, and cost is saved.
本发明公开了一种二次结构前置施工方法,包括以下步骤:步骤1:定位放线并进行钢筋绑扎,水电管、箱预埋,钢筋网片锚入一次结构梁柱墙内,钢筋网片上端不应锚入梁内,防止梁受力后钢筋网片弯曲导致泡沫混凝土墙裂缝,钢筋网片上端与挤塑板底齐平即可;步骤2:一次结构的模板和二次结构的模板同时支设;步骤3:浇筑二次结构;所述二次结构为泡沫混凝土墙;步骤4:待步骤3中的泡沫混凝土墙终凝后,再浇筑一次结构混凝土;步骤5:拆模;步骤6:拆模后拆除钢管支架前。本发明一次结构、二次结构同时施工同时完成,实现无缝衔接,避免了较长时间的工序间隔,大量缩短工期,节约成本。
The invention discloses a secondary structure preposed construction method which comprises the following steps: step 1, positioning and paying off, binding steel bars, pre-burying water and electricity pipes and boxes, anchoring a steel bar mesh into a primary structure beam column wall, preventing the upper end of the steel bar mesh from being anchored into a beam, and preventing the steel bar mesh from being bent after the beam is stressed to cause cracks of a foam concrete wall; the upper end of the reinforcing mesh is flush with the bottom of the extruded sheet; 2, a formwork of a primary structure and a formwork of a secondary structure are erected at the same time; 3, a secondary structure is poured; the secondary structure is a foam concrete wall; fourthly, after the foam concrete wall in the third step is finally set, structural concrete is poured again; step 5, removing the mold; and 6, removing the steel pipe bracket after the mold is removed. The primary structure and the secondary structure are constructed and completed at the same time, seamless connection is achieved, a long process interval is avoided, the construction period is greatly shortened, and cost is saved.
本发明公开了一种二次结构前置施工方法,包括以下步骤:步骤1:定位放线并进行钢筋绑扎,水电管、箱预埋,钢筋网片锚入一次结构梁柱墙内,钢筋网片上端不应锚入梁内,防止梁受力后钢筋网片弯曲导致泡沫混凝土墙裂缝,钢筋网片上端与挤塑板底齐平即可;步骤2:一次结构的模板和二次结构的模板同时支设;步骤3:浇筑二次结构;所述二次结构为泡沫混凝土墙;步骤4:待步骤3中的泡沫混凝土墙终凝后,再浇筑一次结构混凝土;步骤5:拆模;步骤6:拆模后拆除钢管支架前。本发明一次结构、二次结构同时施工同时完成,实现无缝衔接,避免了较长时间的工序间隔,大量缩短工期,节约成本。
Secondary structure preposed construction method
一种二次结构前置施工方法
ZHU YUTAN (Autor:in)
29.11.2024
Patent
Elektronische Ressource
Chinesisch
Construction method for preposed prefabricated concrete water stop ridge
Europäisches Patentamt | 2023
|Large-span bidirectional orthogonal sheet type primary truss preposed construction method
Europäisches Patentamt | 2023
|Preposed press-wheel device of road roller, and operation method of preposed press-wheel device
Europäisches Patentamt | 2015
|Tidal reach preposed in-situ water ecological restoration structure and method
Europäisches Patentamt | 2021
|Turnover bottom board of grinding wheel preposed wedge type fat edge grinding machine
Europäisches Patentamt | 2015
|