Construction method for newly adding ground ring beam for transforming old wall
The invention relates to a construction method for newly adding a ground ring beam for transforming an old wall. The construction method comprises the following steps that S1, a supporting position is determined and marked; s2, manufacturing a supporting device; s3, chiseling off the wall body at the supporting position; s4, adjusting the pressure value of the jack; s5, chiseling away the remaining wall between the supporting devices; and S6, the newly-added ground ring beam is poured. After the upper wall body is supported through the supporting devices, the newly-added ground ring beam is integrally poured, segmented construction is not needed, the continuity of the newly-added ground ring beam can be guaranteed, and therefore the construction quality is guaranteed, and the construction period is shortened; and the pressure value of the jack is adjusted to the load value to be borne, so that the supporting stability can be ensured.
本发明涉及一种用于改造旧墙体新增地圈梁的施工方法,包括以下步骤:S1、确定支撑位置,并标记;S2、制作支撑装置;S3、凿除支撑位置的墙体;S4、调整千斤顶压力数值;S5、凿除支撑装置之间剩余墙体;S6、浇筑新增地圈梁。本发明通过支撑装置支撑上部墙体后,整体浇筑新增地圈梁,不用进行分段施工,可保证新增地圈梁的连续性,从而保证施工质量,缩短施工工期,施工中根据上部墙体荷载计算每个支撑装置的受力,将千斤顶的压力数值调整至应承受的荷载值,可保证支撑的稳定性。
Construction method for newly adding ground ring beam for transforming old wall
The invention relates to a construction method for newly adding a ground ring beam for transforming an old wall. The construction method comprises the following steps that S1, a supporting position is determined and marked; s2, manufacturing a supporting device; s3, chiseling off the wall body at the supporting position; s4, adjusting the pressure value of the jack; s5, chiseling away the remaining wall between the supporting devices; and S6, the newly-added ground ring beam is poured. After the upper wall body is supported through the supporting devices, the newly-added ground ring beam is integrally poured, segmented construction is not needed, the continuity of the newly-added ground ring beam can be guaranteed, and therefore the construction quality is guaranteed, and the construction period is shortened; and the pressure value of the jack is adjusted to the load value to be borne, so that the supporting stability can be ensured.
本发明涉及一种用于改造旧墙体新增地圈梁的施工方法,包括以下步骤:S1、确定支撑位置,并标记;S2、制作支撑装置;S3、凿除支撑位置的墙体;S4、调整千斤顶压力数值;S5、凿除支撑装置之间剩余墙体;S6、浇筑新增地圈梁。本发明通过支撑装置支撑上部墙体后,整体浇筑新增地圈梁,不用进行分段施工,可保证新增地圈梁的连续性,从而保证施工质量,缩短施工工期,施工中根据上部墙体荷载计算每个支撑装置的受力,将千斤顶的压力数值调整至应承受的荷载值,可保证支撑的稳定性。
Construction method for newly adding ground ring beam for transforming old wall
一种用于改造旧墙体新增地圈梁的施工方法
JIN ZHIBO (Autor:in) / JIA YAPING (Autor:in) / GUO JIAN (Autor:in) / WU MENG (Autor:in) / HE QINGYI (Autor:in) / DIAO BOWEN (Autor:in) / LI YANTONG (Autor:in) / BU MENGMENG (Autor:in) / WANG LICHAO (Autor:in) / CHEN HANYI (Autor:in)
13.12.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Construction method for newly-added ground ring beam of old building
Europäisches Patentamt | 2024
|Special elevator adding and transforming construction method
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2024
|Europäisches Patentamt | 2022
|