Building basement caisson construction method
The invention discloses a caisson construction method for a building basement. The caisson construction method comprises the steps that a prefabricated basement and a construction temporary supporting structure are placed above a basement area to be constructed; soil excavation is conducted on the basement area to be constructed, and excavated soil is output outwards; in the excavation process, soil below vertical stress components and peripheral blocking components in the prefabricated basement and the construction temporary supporting structure is excavated step by step in batches, so that the prefabricated basement and the construction temporary supporting structure sink synchronously; and when the basement and the construction temporary supporting structure sink to the preset depth, the prefabricated vertical stress component in the basement is connected with a foundation or a pile foundation, a bottom plate is poured, and building basement construction is completed. According to the construction method of the building basement caisson, the stability of the overall structure can be kept all the time on the basis that fewer building materials are adopted, and therefore the construction method is more efficient, safer and lower in cost.
本申请公开了一种建筑地下室沉箱施工方法,包括将预制的地下室及施工临时支撑结构放置于待施工地下室区域的上方;对所述待施工地下室区域进行土体开挖,向外输出开挖出来的土;在开挖的过程中,分批逐步挖除所述预制的地下室及施工临时支撑结构中的竖向受力构件和外围阻挡部件下面的土,使所述预制的地下室及施工临时支撑结构同步下沉;当所述地下室及施工临时支撑结构下沉到预设深度时,将所述预制的地下室中的竖向受力构件与基础或桩基连接在一起,并浇筑底板,完成建筑物地下室施工。上述建筑地下室沉箱施工方法,能够在采用更少建筑材料的基础上,时刻保持整体结构的稳定性,因此更加高效安全且成本更低。
Building basement caisson construction method
The invention discloses a caisson construction method for a building basement. The caisson construction method comprises the steps that a prefabricated basement and a construction temporary supporting structure are placed above a basement area to be constructed; soil excavation is conducted on the basement area to be constructed, and excavated soil is output outwards; in the excavation process, soil below vertical stress components and peripheral blocking components in the prefabricated basement and the construction temporary supporting structure is excavated step by step in batches, so that the prefabricated basement and the construction temporary supporting structure sink synchronously; and when the basement and the construction temporary supporting structure sink to the preset depth, the prefabricated vertical stress component in the basement is connected with a foundation or a pile foundation, a bottom plate is poured, and building basement construction is completed. According to the construction method of the building basement caisson, the stability of the overall structure can be kept all the time on the basis that fewer building materials are adopted, and therefore the construction method is more efficient, safer and lower in cost.
本申请公开了一种建筑地下室沉箱施工方法,包括将预制的地下室及施工临时支撑结构放置于待施工地下室区域的上方;对所述待施工地下室区域进行土体开挖,向外输出开挖出来的土;在开挖的过程中,分批逐步挖除所述预制的地下室及施工临时支撑结构中的竖向受力构件和外围阻挡部件下面的土,使所述预制的地下室及施工临时支撑结构同步下沉;当所述地下室及施工临时支撑结构下沉到预设深度时,将所述预制的地下室中的竖向受力构件与基础或桩基连接在一起,并浇筑底板,完成建筑物地下室施工。上述建筑地下室沉箱施工方法,能够在采用更少建筑材料的基础上,时刻保持整体结构的稳定性,因此更加高效安全且成本更低。
Building basement caisson construction method
一种建筑地下室沉箱施工方法
SHAN YINMU (Autor:in) / LIU XIAOGUANG (Autor:in) / JIANG MIN (Autor:in)
27.12.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Basement bearing platform and caisson construction shaping model
Europäisches Patentamt | 2022
|Method for building basement through checkerboard type layout open caisson method
Europäisches Patentamt | 2024
|CAISSON CONSTRUCTION MANAGEMENT DEVICE AND CAISSON CONSTRUCTION METHOD
Europäisches Patentamt | 2017
|Building dense region underground-space-building caisson construction method
Europäisches Patentamt | 2015
|Open caisson construction method and open caisson structure